Changes to Project Scope Sample Clauses

Changes to Project Scope. Customer may request changes to the scope of a Statement of Work. Any changes to the scope of a Statement of Work will result in a change order to such Statement of Work or a new Statement of Work. Any scope changes will be made pursuant to the terms set forth in a Statement of Work, to be mutually agreed upon by the Parties.
AutoNDA by SimpleDocs
Changes to Project Scope. If the City authorizes an increase or decrease in the scope of the Project or the Total Authorized Design Value of the Project, the Base Fee will be adjusted accordingly, based on justification from the Wage Rates or as mutually agreed upon.
Changes to Project Scope. Any changes to the project which require The startup club to (i) perform additional work exceeding the scope contemplated under this agreement, and/or (ii) extend the timeline of the project, must fi rst be agreed to in writing by both The startup club and Client (which is understood to include email communications).
Changes to Project Scope. If client wants to change the scope of work after acceptance of this agreement, client shall send designer a written change order (detailed, in one email) describing the requested changes in detail. Within ten (10) days of receiving a change order, designer will respond with a statement proposing designers availability, additional fees, changes to delivery dates, and any modification to the terms and conditions. Designer will evaluate each change order at its standard rate and charges. Client will be billed on a time and materials basis at XxXxxxx.xx hourly rate of $50 per hour inc. gst. Such charges shall be in addition to all other amount payable under this agreement, despite any maximum budget, contract price or final price identified. Designer may extend or modify any delivery schedule or deadlines in the agreement as may be required by such changes. Client will have ten (10) days to respond in writing accepting or rejecting the new proposal. If client rejects the proposal, designer will not be obligated to perform any services beyond those in the original agreement. If the proposal for the amended project scope from XxXxxxx.xx is rejected by the Client, XxXxxxx.xx is not obliged to perform any services beyond those in the Original Agreement. XxXxxxx.xx reserves the right to extend or modify any delivery schedule or deadlines in the agreement as may be required by such changes.
Changes to Project Scope. Customer may request changes to the scope of a Statement of Work. Any changes to the scope of a Statement of Work shall result in a change order to such Statement of Work or a new Statement of Work. Notwithstanding the foregoing, if there are any changes to the scope of a Statement of Work and the changes result in an increase in the fees up to ten thousand dollars ($10,000.00) or ten percent (10%) of the estimated total cost, whichever is less, then OPIE will continue to provide the professional services, including the additional work, under such Statement of Work without the need to execute a change order or a new Statement of Work. Customer will pay OPIE for all services provided under a Statement of Work. All change orders and new Statement of Work will also be billed on a time and materials basis. Any scope changes shall be made pursuant to the terms set forth in a Statement of Work, to be mutually agreed upon by the Parties.
Changes to Project Scope. 5. The Municipality, at its election, may request that changes be made or work added to the Project during the period of construction, provided the Municipality agrees in writing to pay any additional cost plus an amount not to exceed ten (10%) percent of such construction cost to cover all necessary engineering, inspection and administrative costs associated therewith, unless specified otherwise. All such requests shall be subject to MaineDOT approval. In the event that the cost of these changes or work are approved for federal participation, the Municipality’s additional cost may be reduced by the amount of the federal contribution.
Changes to Project Scope. If Client wants to change the Scope of Work after acceptance of this Agreement, Client shall send Designer a written Change Order describing the requested changes in detail. Within ten (10) days of receiving a Change Order, Designer will respond with a statement proposing designers availability, additional fees, changes to delivery dates, and any modification to the Terms and Conditions. Designer will evaluate each Change Order at its standard rate and charges. Client will be billed on a time and materials basis at Designers hourly rate of sixty-five ($65) dollars per hour. Such charges shall be in addition to all other amount payable under this Agreement, despite any maximum budget, contract price or final price identified. Designer may extend or modify any delivery schedule or deadlines in the Agreement as may be required by such changes. Client will have ten (10) days to respond in writing accepting or rejecting the new proposal. If Client rejects the proposal, Designer will not be obligated to perform any services beyond those in the original Agreement.
AutoNDA by SimpleDocs
Changes to Project Scope. As to any part of the Project Scope not finalized or completed as of the Effective Date and any change in the Project Scope after the Effective Date shall be submitted to the Authority for review and written approval of the Authority Representative. Notwithstanding the foregoing, changes to the Project Scope that are less than ten percent of the Project Costs or $10,000, whichever is smaller, shall not require the approval of the Authority.
Changes to Project Scope. Change Request: If Client wants to change the Scope of Work after acceptance of this Agreement, Client shall send Designer a written Change Order describing the requested changes in detail. Within five (5) days of receiving a Change Order, Designer will respond with a statement proposing designers availability, additional fees, changes to delivery dates, and any modification to the Terms and Conditions. Designer will evaluate each Change Order at its standard rate and charges.
Changes to Project Scope. The Municipality will consult with MaineDOT and PACTS before implementing any adjustments to the Project scope.