Common use of Changes to Critical Path Clause in Contracts

Changes to Critical Path. (a) Any changes to the critical path of the Works Schedule initiated by Project Co which affect the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by HMQ. Subject to the terms of Schedule 22 – Variation Procedure, any HMQ approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of the Contract Time or an addition to the Guaranteed Price.

Appears in 1 contract

Sources: Project Agreement

Changes to Critical Path. (a) Any changes to the critical path of the Works Schedule initiated by Project Co which affect the Scheduled Substantial Completion Date, the Scheduled PGW Substantial Completion Date, the Scheduled Final Completion Date or the Scheduled PGW Final Completion Date must be approved in writing by HMQ. Subject to the terms of Schedule 22 – Variation Procedure, any HMQ approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of the Contract Time time or an addition to the Guaranteed Price.

Appears in 1 contract

Sources: Project Agreement

Changes to Critical Path. (a) Any changes change to the critical path of the Works Schedule initiated by Project Co which affect affects a Scheduled Phase Completion Date, the Scheduled Tower Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date must be approved in writing by HMQSMH. Subject to the terms of Schedule 22 – Variation Procedure, any HMQ SMH approval of such changes to the critical path does not entitle Project Co to a Variation, an extension of the Contract Time time or an addition to the Guaranteed Price.

Appears in 1 contract

Sources: Project Agreement