Changes and Extra Work. 7.1 Owner may require or approve changes within the general scope of Contractor's Services hereunder by a written Change Order, or may request extra work to be mutually agreed upon. 7.2 In the event any such change causes an increase or decrease in the time for performing Contractor's Services, the parties shall agree upon an equitable adjustment of the schedule obligations to the extent they are affected by such change. Contractor's staffing plan that is mutually agreed upon in accordance with and for the purposes described in Paragraph I a of Attachment B and the determination of the applicable Hourly Unit Rate Payments under that Paragraph shall also be subject to an equitable adjustment to the extent affected by any such scope change or by any changed circumstances outside of Contractor's control, including Force Majeure events, changes in law, and Owner's delay in performing its obligations hereunder. 7.3 Owner reserves the right to direct Contractor to reduce the number of Contractor's personnel assigned to the Project at any time upon thirty (30) days prior written notice to Contractor of such reduction. Further, Owner reserves the right to reduce the number of PCS-sites and/or MSCs assigned to Contractor at any time. Any such reductions shall be without penalty to Owner.
Appears in 2 contracts
Sources: Project and Construction Management Services Agreement (Tritel Finance Inc), Project and Construction Management Services Agreement (Tritel Finance Inc)