Common use of Changes and Extra Work Clause in Contracts

Changes and Extra Work. District may make changes within the general scope of this Agreement and may request Engineer to perform additional services not covered by the Scope of Work defined in a TAF. If Engineer believes that any proposed change or direction given by District causes an increase or decrease in the cost and/or the time required for the performance of this Agreement, Engineer shall so notify District in writing no later than five days after the date of receiving notification of a proposed change or the changed direction. Engineer shall perform such services and will be paid for such services pursuant to a negotiated and mutually agreed change signed by the Parties to this Agreement. If Engineer determines that any work beyond the Scope of Work is necessary for completion of the Project, Engineer shall notify District and receive approval prior to starting that work. If the Parties do not agree whether Engineer is entitled to additional compensation or the extent of such compensation for work Engineer determines is extra or changed work, Engineer shall proceed with the work and the issue of the compensation shall be reserved for later determination as provided in Section 9 of this Agreement.

Appears in 2 contracts

Sources: Engineering Services Agreement, Engineering Services Agreement

Changes and Extra Work. The District may make changes within the general scope of this Agreement and may request the Engineer to perform additional services not covered by the Scope original scope of Work work defined in a TAF. If the Engineer believes that any proposed change or direction given by the District causes an increase or decrease in the cost and/or the time required for the performance of the Work defined in a TAF or this Agreement, the Engineer shall so notify the District in writing no later than five days after the date of receiving notification of a proposed change or the changed direction. The Engineer shall perform such services and will be paid for such services pursuant to a negotiated and mutually agreed change order signed by the Parties to this Agreement. If the Engineer determines that any work beyond the Scope of Work is necessary for completion of the Project, the Engineer shall notify the District and receive written approval prior to starting that work. If the Parties do not agree whether the Engineer is entitled to additional compensation or the extent of such compensation for work the Engineer determines is extra or changed work, the Engineer shall proceed with the work and the issue of the compensation shall be reserved for later determination as provided in Section 9 of this Agreement.

Appears in 1 contract

Sources: Engineering Services Agreement