Bus Work. The 69kV low bus will be extended to the west. The new 69kV main bus will be 3” Al with 1192 Al wire taps. The wire taps to all PT’s and arresters will be 336 Al. Control House – Three (3) new control panels will be installed in the west end of the control house. The new AC supply cable to GCB 6050 will come from a single pole 30A breaker on AC Dist Panel C. Control Cables – The following new cables will be installed. These will be installed from the control house to the new equipment via the existing precast concrete trench and new conduits. Two (2) 19/c #12 control cables Two (2) 9/c #9 CT cables One (1) 2/c #10 AC One (1) 10c/#9 awg metering secondary cable One (1) 10c/#9 awg metering secondary cable Miscellaneous – 48kV MCOV surge arresters will be located 18” from the insulators on the pothead structure. One (1) spline ball will be installed. All new equipment will be connected to the existing ground grid according to LIPA’s construction standards.
Appears in 3 contracts
Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement