Board-Requested Changes Sample Clauses
Board-Requested Changes. If the Board requests changes in the Contract Documents that would materially affect the completion of the Work by lengthening the critical path of the Overall Project Schedule, the Design Professional shall recommend the appropriate number of additional days to be considered in the Change Order. The CMR expressly agrees that any monetary remedy associated with such extensions of time shall be no greater than the actual direct costs incurred by the CMR.