Assigned Project Roster. (i) Contractor shall designate a Construction Manager, Project Manager, a Project Engineer, and a Startup Manager for the Work, each of whom shall constitute a “Contractor Representative.” All natural persons assigned by Contractor to perform any of Contractor’s obligations shall be fully qualified to perform the tasks assigned them. (ii) At least one Contractor’s Representative shall be present on the Site during working hours and at all times the Work is in progress, and any orders 23 or instructions which Company or Company’s Representative may give to the Contractor’s Representative shall be deemed to have been given to Contractor. (iii) Company shall have the right, in its sole discretion, to approve or disapprove, prior to their selection by Contractor, Contractor’s selections for Construction Manager, Project Manager, Project Engineer and/or Startup Manager. (iv) If Contractor intends to remove or change its Construction Manager, Project Manager, Project Engineer and/or Startup Manager assigned to the Work or reassign any such personnel to another project, Contractor shall give Company fifteen (15) days advance written notice of Contractor’s intentions. Company shall give due consideration to any request by Contractor to replace such persons and shall respond within fifteen (15) days to any such requests. Contractor shall not replace its Construction Manager, Project Manager, Project Engineer and/or Startup Manager assigned to the Work without the prior written consent of Company, which consent shall not be unreasonably withheld or delayed.
Appears in 1 contract
Sources: Engineering, Procurement and Construction Contract (Chugach Electric Association Inc)
Assigned Project Roster. (i) Contractor shall designate a Construction Manager, Project Manager, a Project Engineer, and a Startup Manager for the Work, each of whom shall constitute a “Contractor Representative.” All natural persons assigned by Contractor to perform any of Contractor’s obligations shall be fully qualified to perform the tasks assigned them.
(ii) At least one Contractor’s Representative shall be present on the Site during working hours and at all times the Work is in progress, and any orders 23 or instructions which Company or Company’s Representative may give to the Contractor’s Representative shall be deemed to have been given to Contractor.
(iii) Company shall have the right, in its sole discretion, to approve or disapprove, prior to their selection by Contractor, Contractor’s selections for Construction Manager, Project Manager, Project Engineer and/or Startup Manager.
(iv) If Contractor intends to remove or change its Construction Manager, Project Manager, Project Engineer and/or Startup Manager assigned to the Work or reassign any such personnel to another project, Contractor shall give Company fifteen (15) days advance written notice of Contractor’s intentions. Company shall give due consideration to any request by Contractor to replace such persons and shall respond within fifteen (15) days to any such requests. Contractor shall not replace its Construction Manager, Project Manager, Project Engineer and/or Startup Manager assigned to the Work without the prior written consent of Company, which consent shall not be unreasonably withheld or delayed.