Additional Specifications Applicable to Connections. 4.5.1 The following specifications apply to connections of CLEC’s Conduit to AT&T-22STATE’s Conduit System:
4.5.1.1 CLEC will be permitted to connect its Conduit or Duct only at an AT&T-22STATE Manhole. No attachment will be made by entering or breaking into Conduit between Manholes. All necessary work to install CLEC Facilities will be performed by CLEC or its contractor at CLEC’s expense. In no event shall CLEC or its contractor “core bore” or make any other modification to AT&T- 22STATE Manhole(s) without the prior written approval of AT&T-22STATE, which approval will not be unreasonably delayed or withheld.
4.5.1.2 If CLEC constructs or utilizes a Duct connected to AT&T-22STATE’s Manhole, the Duct and all connections between that Duct and AT&T-22STATE’s Manhole shall be sealed, to the extent practicable, to prevent the entry of gases or liquids into AT&T-22STATE’s Conduit System. If CLEC’s Duct enters a building, it shall also be sealed where it enters the building and at all other locations necessary to prevent the entry of gases and liquids from the building into AT&T- 22STATE’s Conduit System.
Additional Specifications Applicable to Connections. The following specifications apply to connections of Licensee's conduit to BellSouth's conduit system:
3.5.1 Licensee will be permitted to connect its conduit or duct only at the point of a BellSouth manhole. No attachment will be made by entering or breaking into conduit between manholes. All necessary work to install Licensee facilities will be performed by Licensee or its contractor at Licensee’s expense. In no event shall Licensee or its contractor “core bore” or make any other modification to BellSouth manhole(s) without the prior written approval of BellSouth, which approval will not be unreasonably delayed or withheld.
3.5.2 BellSouth may monitor, at Licensee’s expense, the entrance and exit of Licensee's facilities into BellSouth's manholes and the placement of Licensee's facilities in BellSouth's manholes.
3.5.3 If Licensee constructs or utilizes a duct connected to ▇▇▇▇▇▇▇▇▇'s manhole, the duct and all connections between that duct and ▇▇▇▇▇▇▇▇▇'s manhole shall be sealed, to the extent practicable, to prevent the entry of gases or liquids into BellSouth's conduit system. If Licensee's duct enters a building, it shall also be sealed where it enters the building and at all other locations necessary to prevent the entry of gases and liquids from the building into BellSouth's conduit system.
Additional Specifications Applicable to Connections. The following specifications apply to connections of Licensee’s Conduit to AT&T’s Conduit System:
3.5.1 Licensee will be permitted to connect its Conduit or Duct only at the point of an AT&T Manhole. No attachment will be made by entering or breaking into Conduit between Manholes. All necessary work to install Licensee Facilities will be performed by Licensee or its contractor at Licensee’s expense. In no event shall Licensee or its contractor “core bore” or make any other modification to AT&T Manhole(s) without the prior written approval of AT&T, which approval will not be unreasonably delayed or withheld.
3.5.2 AT&T may monitor, at Licensee’s expense, the entrance and exit of Licensee’s Facilities into AT&T’s Manholes and the placement of Licensee’s Facilities in AT&T’s Manholes.
3.5.3 If Licensee constructs or utilizes a Duct connected to AT&T’s Manhole, the Duct and all connections between that Duct and AT&T’s Manhole shall be sealed, to the extent practicable, to prevent the entry of gases or liquids into AT&T’s Conduit System. If Licensee’s Duct enters a building, it shall also be sealed where it enters the building and at all other locations necessary to prevent the entry of gases and liquids from the building into AT&T’s Conduit System.
Additional Specifications Applicable to Connections. The following specifications apply to connections of MCIm's conduit to BellSouth's conduit system:
1.3.5.1 MCIm will be permitted to connect its conduit or duct only at the point of a BellSouth manhole. No attachment will be made by entering or breaking into conduit between manholes. All necessary work to install MCIm facilities will be performed by MCIm or its contractor at MCIm's expense. In no event shall MCIm or its contractor "core bore" or make any other modification to BellSouth manhole(s) without the prior written approval of BellSouth, which approval will not be unreasonably delayed or withheld. Attachment VI - 12 MCIm - BellSouth Mississippi Interconnection Agreement
1.3.5.2 BellSouth may monitor, at MCIm's expense, the entrance and exit of MCIm's facilities into BellSouth's manholes and the placement of MCIm's facilities in BellSouth's manholes.
1.3.5.3 If MCIm constructs or utilizes a duct connected to BellSouth's manhole, the duct and all connections between that duct and BellSouth's manhole shall be sealed, to the extent practicable, to prevent the entry of gases or liquids into BellSouth's conduit system. If MCIm's duct enters a building, it shall also be sealed where it enters the building and at all other locations necessary to prevent the entry of gases and liquids from the building into BellSouth's conduit system.