ADDITIONAL CONDITIONS नमुना कलम
ADDITIONAL CONDITIONS. 8.1 Dismantling material maximum quantity re-use in all aluminum sections and particle board /doors /window.
8.2 Existing aluminum partition extends and particle board sheet as per required shade direction by EE/work -in-charge.
8.3 Inspection of materials and work: All the materials brought to the site by the contractor for use in the work as well as fabricated work shall be subject to inspection and approval by the EE/Work in - charge.
8.4 Removal of rejected materials: In case any materials are rejected by the Engineer-in-Charge, the same shall be removed from the site within 48 hours, failing which the same may be got removed by the Engineer-in-charge at the risk and cost of the contractor.
8.5 Manufacturer’s Test Certificate: The contractor shall, if required by the Engineer in charge produce Manufacture’s Test Certificate for any material of particular batch of materials supplied by him. The test(s) carried out shall be as per relevant specifications/ BIS Code.
8.6 Contractor should ensure the availability of material at site duly tested as per specifications and approved by the Engineer-in-charge. In no case the dismantling etc. should be carried out before the availability of approved quality of material. If contractor fails to follow this instruction a penalty of Rs.1000/- per day delay for this fault shall be recovered. The decision of Engineer-in-Charge shall be final and binding.
8.7 Wherever the malba / rubbish occurs on account of work at upper floors / roof, the same shall be brought down through stair case or with some mechanical arrangement only and shall not be thrown to the ground directly from upper floors and has to be disposed off at specified dumping point in the area. In no case malba / rubbish / unserviceable material or Construction material shall be stacked or dumped near the staircase / path /road / lawn / outside premises even for temporarily purpose.
8.8 Unless and until specified in the item the contractor shall make his own arrangement for lifting / hoisting / placing of steel girders / steel sections by suitable arrangement either manually or by mechanical crane etc. as approved by the Engineer-in-charge upto all heights in the building at no extra cost.
8.9 The contractor shall stack the building materials away from the building at site as approved by the Engineer-in-charge and nothing extra for lead / lift of material for bringing the materials manually in the premises shall be paid.
8.10 The dismantled materials received...