WTG Mechanical Completion definition

WTG Mechanical Completion has the meaning set forth in Section 7.4.
WTG Mechanical Completion means, as to a WTG, the achievement of the following:
WTG Mechanical Completion means, as to a WTG, the achievement of the following: Closing Completion and valid delivery and acceptance by Owner of a Closing Completion Certificate with respect to the Facility; subject to Punch List Items, such WTG is assembled, erected and installed so as to be demonstrably completed in accordance with the Technical Specifications, the WTG Mechanical Completion Certificate set forth in Exhibit 17A, the Wind Turbine Supply Contract and the other requirements of this Agreement; subject to Punch List Items, all materials and equipment associated with such WTG have been installed in accordance with the Technical Specifications and verified in accordance with the installation checklists set forth in Exhibit 14; Contractor has prepared and submitted a list of Punch List Items with respect to such WTG or other component; the WTG is ready to commence Commissioning; Electrical Works Completion with respect to the Electric Works circuit line to which the WTG is connected and valid delivery and acceptance by Owner of an Electric Works Completion Certificate with respect to such circuit; Turbine Vendor acknowledges that all Work necessary for Turbine Vendor to commence to Commission the WTG has been successfully completed by Contractor; and Owner has accepted or is deemed to have accepted a WTG Mechanical Completion Certificate with respect to such WTG pursuant to Section 7.8.

Examples of WTG Mechanical Completion in a sentence

  • During the period from WTG Mechanical Completion to Final Completion, Contractor’s performance of the Work shall not unreasonably interfere with the Commissioning of the WTGs or the commercial operation of the Project.

  • In connection with and as a condition to the achievement of Electrical Works Completion for a particular circuit and the achievement of WTG Mechanical Completion as to each WTG, Contractor shall develop a list (each, an “Interim Punch List”) setting forth parts of the Work which remain to be performed in order to confirm that the Work fully complies with the terms of this Agreement.

  • Contractor shall cause Project Mechanical Completion to occur timely following WTG Mechanical Completion of each of the WTGs and otherwise in accordance with the requirements of this Agreement.

  • The final and effective Exhibit 4.1.1 shall be delivered to Owner by Contractor no later than the date of WTG Mechanical Completion for the first WTG.

  • Sufficiently in advance of the first WTG Mechanical Completion Date to allow Owner to purchase timely and assemble and store same at the Site at or prior to commercial operation of the Project, Contractor shall provide a general list in Microsoft Excel format of recommended spare parts necessary to operate and maintain the Project (excluding spare parts comprising the Owner-Furnished Equipment) (the “Spare Parts”) and Consumable Parts necessary to operate and maintain the Project.

  • On the Effective Date, Contractor shall commence and shall thereafter diligently pursue the Work assigning to it a priority that will permit the attainment of Access Road Completion on or before the Guaranteed Access Road Completion Date, and WTG Mechanical Completion for all WTGs on or before the Guaranteed Mechanical Completion Date.

  • The Contractual Documents also apply: - regardless of where the ADVERTISER's current or future Channel is hosted, as well as to all Channels that may be operated by the ADVERTISER, - in the event that the ADVERTISER divides its Channel into several different Channels, creates or acquires a new Channel.

  • Protocol for the pre functional test of each WTG prior to energization and synchronization (prior to WTG Mechanical Completion) to be provided by bidders.

  • Contractor shall cause WTG Mechanical Completion with respect to each WTG to occur on or before the Guaranteed Mechanical Completion Date and otherwise in accordance with the requirements of this Agreement.

  • Subject to Owner’s rights pursuant to Sections 6.8 and 13.1, payment of Mechanical Completion Delay Liquidated Damages is the exclusive remedy for delays in achieving WTG Mechanical Completion.