Examples of Work to Commence in a sentence
Work to Commence It is hereby understood and agreed that the wok under this Agreement shall not commence until after the issuance of the Notice to Proceed.
Interconnection Customer • None SCHEDULE J SCHEDULE OF WORK Item Description Responsibility PJM Network Upgrade # Work to Commence Work to be completed on or before 1 Install a SEL-411L as Current Differential Line protection on L94701 and make the existing primary relay, SEL- 311L, the secondary relay.
SCHEDULE J SCHEDULE OF WORK Item Description Responsibility PJM Network Upgrade # Work to Commence Work to be completed on or before 1 Replace the 138kV breaker for L15507 with a 138kV breaker with minimum rating of 3000A continuous and 63kA interrupting capacity.
Interconnected Transmission Owner N6400 Anytime after effective date of this ICSA 1,065 days from ICSA effective date1 Item Description Responsibility PJM Network Upgrade # Work to Commence Work to be completed on or before 7 Reconfigure JungleMUX fiber ring connections at the STA 12 Dresden substation.
Interconnected Transmission Owner N5756 Anytime after effective date of this ICSA 1,065 days from ICSA effective date1 Item Description Responsibility PJM Network Upgrade # Work to Commence Work to be completed on or before 3 Design, procure, and construct L1202 from the cut-in location on the edge of the existing right-of- way to tap point on existing line.
Interconnected Transmission Owner N4601 Any time after effective date of this CSA March 31, 2023 Item Description Responsibility PJM Network Upgrade # Work to Commence Work to be completed on or before 5 Evaluate the adequacy of existing station batteries and battery chargers due to new SEL-2440 installed in breaker control cabinet.
Work to Commence on July 17, 2017; Substantial Completion September 29, 2017 Proposal Requested Pre-Construction # GMP v Study # Construction Management Fee Lump Sum v NTE # General Conditions Lump Sum # NTE v Pre-Construction Compensation Lump Sum # NTE # Performance/Payment Bond Required YES v NO # Prof.
Interconnection Customer N6400 Anytime after effective date of this ICSA 04/01/2022 Item Description Responsibility PJM Network Upgrade # Work to Commence Work to be completed on or before 19 Design, procure, and construct the TSS 924 Three Rivers substation, including two generator step-up transformers, two 345 kV circuit breakers, two 345 kV line terminations, protective relaying and control equipment, and telemetry.
If you are then happy for works to commence, please contact our team to complete our Express Request for Work to Commence form.
Work to Commence after Official Start Date No work is to be undertaken by the Contractor prior to the official starting date.