The Consultant shall complete its Work within the Work Order Schedule, including any established milestones, task completion dates, and deliverables set forth in the Work Order.
If the Consultant considers the Task Directive to be a change to the Scope of Work, Work Order Schedule, or Work Order Price, then prior to performing any Work, the Consultant shall submit to the Project Representative a written request for a Work Order Change.
Schedule A: Work Order Schedule B: Project Schedule Schedule C: Insurance and Indemnity Requirements Exhibit A - Plans and Specifications Organization of the Specifications into divisions, sections and articles, and arrangement of Plans shall not control the Contractor in dividing the work among Subcontractors or in establishing the extent of work to be performed by any trade.
In the event an item identified below does not occur in the manner or time frame shown, such circumstance shall constitute a Change Request that may require an adjustment to the Work Order (Schedule and/or Fees).
Customer shall reimburse MPOWER for reasonable MPOWER travel and out of pocket expenses for which advance approval has been received from the Customer either as part of and or incidental to an approved Work Order (Schedule X), or for a specific trip requested by Customer.
In the event of any conflict or inconsistency between the documents, interpretation shall be made by referring to these documents in the following order of precedence: • Work Order (Schedule 4, as may be issued by Lilly as part of this Agreement) • Special Terms & Conditions (Schedule 3); • Pricing (Schedule 2); • General Terms & Conditions (Schedule 1); • Supplier Privacy Standard (Schedule 5); and • Information Security Standard (Schedule 6).
The following Schedules are attached to this Attachment F: Schedule F-A – Hosting Services Description Schedule F-B – Form of Work Order Schedule F-C – Operational Representatives for Hosting Services Schedule F-D – TRX Third Party Providers for Hosting Services AMEX is engaging TRX for the purpose of hosting the American Express *, and providing maintenance and support for the product.
Any non-standard Education Services, including on-site visits by Licensor personnel, shall be subject to additional fees and agreed to by the parties and outlined in a Work Order, Schedule or amendment hereto.
County will provide required Equipment and labor resources in a timely manner to meet the Work Order Schedule.
A “Concurrent Delay” is defined as a day on which the critical path of a Work Order Schedule is delayed and which delay is caused by both a Contractor Caused Delay and an Owner Responsible Delay.