Variation Order Request definition

Variation Order Request means a request submitted by Contractor in accordance with Article 16.1;
Variation Order Request means a request submitted by Contractor in accordance with Art. 16.1. ​ ​ FREYR 375 MWh Pilot Battery Plant Contract no.: CNT-FRY-0001 Contract Package: Casting and Unit Cell Assembly ​

Examples of Variation Order Request in a sentence

  • Subject to the limitations which follow from Article 12.1, Company may, regardless of whether Contractor has submitted a Variation Order Request or not, require Contractor to undertake special measures to avoid variation work having an effect on the Contract Schedule or to limit the consequences of Company's variations.

  • If a Variation Order Request is submitted, interest on amounts wrongfully withheld shall be calculated from the date that would have been the due date according to Article 20 if the variation work was part of the Work.

  • The provisions in Article 12 to 16 apply accordingly, provided that the time-limit for presenting a Variation Order Request is 21 Days from the time the circumstances on which the request is based became or ought to have become known to Contractor.

  • In case a time-limit is set forth in relation to Contractor’s right to present a Variation Order Request, Contractor’s right to request an adjustment to the Contract Price and/or the Contract Schedule is conditioned upon presenting a Variation Order Request within such time-limit.

  • Contractor shall provide a Variation Order Request to Company within 14 Days from when Contractor became or reasonably could be expected to become aware of the deviating condition.

  • If the work so required in the opinion of Contractor is not part of his obligations under the Contract, Contractor shall submit a Variation Order Request to Company and as soon as possible thereafter, prepare an estimate in accordance with Art.

  • If the Company rejects the Variation Order Request, it will be signed by a duly authorised representative and transmitted to the Contractor with an instruction not to proceed.

  • Contractor must issue a Variation Order Request within 14 Days after Contractor discovered or ought to have discovered such breach by Company.

  • If the Company approves the Variation Order Request, it will be signed by a duly authorised representative and the Company shall instruct the Contractor how to proceed whereupon the document shall become a Variation Order upon which the Contractor shall proceed as directed.

Related to Variation Order Request

  • Variation Order means any written order, identified as such issued to the Contractor by the Employer under Sub Clause 31.1.

  • DEVIATION ORDER means any order given by the Engineer-in-Charge to effect an alteration, addition or deduction, which does not radically affect the scope and nature of the contract.

  • Change Order Request means a written request or proposal for a Change Order submitted by either Company or Contractor and including:

  • Medication order means a written or verbal order from a

  • adoption order (“gorchymyn mabwysiadu”) means an adoption order within the meaning of section 72(1) of the Adoption Act 1976 or section 46(1) of the Adoption and Children Act 2002;