If there is any reduction in the thermal power output [***] or delay in the performance of the NSSS Thermal Performance Test that is not due to an error or omission of Contractor or its Personnel, Contractor shall re-run the NSSS Thermal Performance Test when such circumstances ▇▇▇▇▇, but the interruption or delay in the performance of the test shall constitute a Change and entitle Contractor to seek a Change Order pursuant to Article 9.
Per APP-GW-T1R-600, the Performance Tests will consist of the following tests: (i) NSSS Thermal Performance Test, (ii) Turbine Generator Output Test (i.e., Net Unit Electrical Output Test) and (iii) Steam Generator Moisture Carryover Test.
If the reduction in the thermal power output [***] or delay is not due to an error or omission of Contractor or its Personnel or Uncontrollable Circumstances, the hours of continuous operation performed prior to such reduction or delay shall be credited toward the period of one hundred (100) hours of continuous operation once the NSSS Thermal Performance Test is resumed.
Thermal Performance Test (Net Electrical Output and Net Heat Rate Tests) Turbine Gross Electrical Output b.
If the reduction in the thermal power output [***] or delay is not due to an error or omission of Contractor or its Personnel or Uncontrollable Circumstances, the hours of continuous operation performed prior to such reduction or delay shall be credited toward the period of [***] of continuous operation once the NSSS Thermal Performance Test is resumed.
The NSSS Thermal Performance Test shall be run during a period of continuous operation of [***].
If during the conducting of the NSSS Thermal Performance Test, the Net Unit Electrical Output, as determined based on a rolling four (4) hour average measured at one hour intervals [***], not due to any action or inaction by Owner or its Personnel, or an event of Force Majeure, then such [***] test shall be re-started once the Net Unit Electrical Output returns to a value [***].
The measurement frequency shall be, at a minimum, every sixty (60) minutes throughout the NSSS Thermal Performance Test.
Such a payment shall not waive or affect any of the other obligations of Contractor under this Agreement including the obligation to complete the NSSS Thermal Performance Test.
The “NSSS Thermal Performance Test”, shall be run at [***] licensed thermal power, if achievable, as indicated by the secondary calorimetric; provided that, if the thermal power output [***] the Unit shall be operating with a Net Unit Electrical Output [***] in order to commence the NSSS Thermal Performance Test.