Target Contract Dates definition
Examples of Target Contract Dates in a sentence
Contractor shall implement such Recovery Plan in order that, to the maximum extent possible, the Target Contract Dates and the Required Contract Dates will be achieved.
Without limiting Contractor’s responsibilities under Article 8, Contractor shall perform the Work in accordance with the Project Schedule with the objective of achieving the Target Contract Dates and the Required Contract Dates.
The Project Schedule, the Target Contract Dates and the Required Contract Dates (including those dates on which Owner is to perform any obligation hereunder as contained in the Project Schedule) may only be modified by agreement of both Parties.
Contractor shall implement such Recovery Plan in order that, to the maximum extent possible, the Target Contract Dates will be achieved.
To the extent that Contractor demonstrates that a Change (or the Change Event necessitating a Change) as described in Section 10.2.2 or Section 10.3 will delay the achievement of the Target Completion Dates, then Owner shall cause a Change Order directing such Change (or resulting from such Change Event) to equitably extend the Target Contract Dates to account for the delay in the critical path of the Work.
Contractor shall be entitled to adjust the Project Schedule at its discretion; provided, however, the Target Contract Dates, and those dates on which PSGC is to perform any obligation hereunder as contained in the Project Schedule may only be modified by a Change Order implemented in accordance with Article 10.
All claims by Contractor for adjustments to the Target Price, the Fee, Performance Targets, Project Schedule (including the Target Contract Dates) and/or other obligations or liabilities of the Parties under this Agreement as a result of any Change shall be supported by verifiable detailed documentation provided to PSGC.
Without limiting Contractor’s responsibility under Section 8.2.3, Contractor shall perform the Work in accordance with the Project Schedule with the objective of achieving the Target Contract Dates.
If the Full Notice to Proceed is delivered to Contractor prior to October 1, 2007, for purposes of the Target Contract Dates and the Project Schedule only, the Commencement Date will be deemed to be October 1, 2007.
To the extent that Contractor demonstrates that a Change (or the Change Event necessitating a Change) as described in Section 10.2.2 or Section 10.3 will delay the achievement of the Target Completion Dates, then PSGC shall cause a Change Order directing such Change (or resulting from such Change Event) to equitably extend the Target Contract Dates to account for the delay in the critical path of the Work.