Substantial Completion and Substantially Complete definition

Substantial Completion and Substantially Complete. The terms "Substantial Completion" and "Substantially Complete" shall each mean the date when all of the following have occurred with respect to the Interior Improvements in question; (i) the construction of the Interior Improvements in question has been substantially completed in accordance with the requirements of this Lease; (ii) the architect responsible for preparing the plans shall have been substantially completed in accordance with the plans and specifications therefor; and (iii) the Building Department of the City of Sunnyvale has completed its final inspection of such improvements and has "signed off" the building inspection card approving such work as complete.
Substantial Completion and Substantially Complete as it relates to the entirety of the Property or any designated portion thereof, as the case may be, shall mean the date, as certified by the architect for the respective portion of the Manassas Gateway Property, when: (a) construction is sufficiently complete in accordance with the construction documents for the respective portion of the Manassas Gateway Property such that the Owner(s) can occupy and utilize the Building(s) or designated portion(s) thereof (including all necessary operating services) for its (their) intended use, subject only to certain unfinished items of construction that are not necessary for the issuance of partial or final certificates of occupancy, residential use permits or non-residential use permits (as applicable), commencement or continuation of rental or other operations on the Manassas Gateway Property (or portion thereof), or the safe use of the Manassas Gateway Property (or portion thereof); and (b) all required governmental inspections applicable to the construction have been conducted and partial or final certificates of occupancy or residential use permits or non-residential use permits (as applicable) allowing for the occupancy of tenants or owners of all or any part of the applicable building have been issued by the applicable governmental authorities and delivered to the Owner(s).
Substantial Completion and Substantially Complete. Are defined in Section 1.1(uu) of the Work Letter.

Examples of Substantial Completion and Substantially Complete in a sentence

  • The definition of "Substantially Completed" shall also apply to the terms "Substantial Completion" and "Substantially Complete".

  • The definition of Substantially Completed shall also define the terms "Substantial Completion" and "Substantially Complete" and any other derivatives thereof Following Substantial Completion of the Second Expansion Improvements (or as soon thereafter as may be reasonably practicable and in any event within thirty (30) days after Substantial Completion), Lessor and Lessee shall inspect the Second Expansion Premises and jointly prepare a "punch list" of agreed items of construction remaining to be completed.

  • C.3.2.6 Develop, test and implement use of electronic monitoring technologies (e.g.,video cameras and sensors) to document catch, bycatch, and discards; includes, but not limited to, installing and maintaining camera equipment, data storage and retrieval, instruction documentation, and processing and analyzing data.

  • The terms "Substantial Completion" and "Substantially Complete" as applicable, shall mean when Tenant's Improvements are sufficiently completed in accordance with the Construction Plans so that Tenant can reasonably use the Premises for the Permitted Use (as described in Section 11 of the Basic Office Lease Information).

  • Substantial Completion and Substantially Complete .........................................................

  • The terms "Substantial Completion" and "Substantially Complete," as applicable, shall mean when Tenant's Improvements are sufficiently completed in accordance with the approved Construction Plans so that Tenant can reasonably use the Premises for the Permitted Use.

  • The terms "Substantial Completion" and "Substantially Complete," as applicable, shall mean when Tenant's Improvements are completed in accordance with the Construction Plans subject only to minor items ("Punch List Items") which may be completed in a manner so that Tenant can reasonably use the Premises for the Permitted Use (as described in Item 12 of the Basic Lease Provisions) without material interruption.

  • The terms Substantial Completion and Substantially Complete as used herein shall have the same meaning.

  • The terms "Substantial Completion" and "Substantially Complete," as applicable, shall mean when Tenant's Improvements are completed in accordance with the Construction Plans subject only to monitor items ("Punch List Items") which may be completed in a manner so that Tenant can reasonably use the Premises for the Permitted Use (as described in Item 12 of the Basic Lease Provisions) without material interruption.


More Definitions of Substantial Completion and Substantially Complete

Substantial Completion and Substantially Complete shall be when the following has occurred: (i) construction of the Building Improvements (without the Tenant Improvements) or Tenant Improvements, as applicable, has been substantially completed in accordance with the requirements of the Final Project Plans excepting only “punch list items” and the Architect has certified such fact in writing on AIA Form #G704-2000 and (ii) a temporary certificate of occupancy is issued by the governmental authority having jurisdiction to issue the same, which such temporary certificate of occupancy allows Tenant to occupy the Building for the Permitted Use at such time as Tenant has obtained the Tenant Approvals (as hereinafter defined); provided, however, if such certificate of occupancy could not be obtained because of the existence or condition of any Tenant Improvements or Tenant Delays (as hereinafter defined), then, for purposes of determining the Base Rent Commencement Date and the Additional Rent Commencement Date only, Substantial Completion of the Building Improvements shall be deemed to occur on the date on which such certificate of occupancy would otherwise have been issued but for such Tenant Delays or Tenant Improvements, which such “deemed to occur” date shall be reasonably determined by the Architect in writing with a statement by the Architect setting forth the basis for his determination. Notwithstanding the foregoing, (a) in no event shall Substantial Completion of the Building Improvements (without the Tenant Improvements) occur prior to the Target Substantial Completion Date, as defined below, and (b) the Substantial Completion Date shall be extended one (1) day for every day that the commencement of the Tenant Improvements, is delayed for a reason other than a Tenant Delay or Force Majeure Delay in commencing the Tenant Improvements on or before June 15, 2017.
Substantial Completion and Substantially Complete. The terms "Substantial Completion" and "Substantially Complete" shall each mean the date when all the EXHIBIT B following have occurred with respect to the Interior Improvements in question: (i) the construction of the Interior Improvements in question has been substantially completed in accordance with the requirements of this Lease, except for Punchlist items which do not unreasonably interfere with Tenant's use of the Premises for Tenant's intended purpose; (ii) the Architect responsible for preparing the plans shall have executed a certificate or statement representing that the Interior Improvements in question have been substantially completed in accordance with the plans and specifications therefor; and (iii) the Building Department of the City of San ▇▇▇▇ or any other approvals required by applicable Law has completed its final inspection of such improvements and has "signed off' the building inspection card approving such work as complete.