Specified Completion Date definition
Examples of Specified Completion Date in a sentence
The Borrower shall fail to complete both Projects by the Specified Completion Date, without extension for any Event of Force Majeure.
Completion of Construction shall occur not later than the Specified Completion Date, subject to Force Majeure.
Design- Builder shall furnish proof of continuous “tail” coverage for 24 months after Specified Completion Date.
Inspecting Engineer shall prepare a report on change orders of more than Two Hundred Fifty Thousand United States Dollars (US$250,000.00) in magnitude and on change orders which in the opinion of Inspecting Engineer are part of a group of changes the magnitude of which aggregate in excess of Five Hundred Thousand United States Dollars (US$500,000.00) or would delay the Completion beyond the Specified Completion Date.
DOE shall have received evidence satisfactory to it, certified by a Responsible Officer of the Borrower, that the completion of each Project is reasonably expected to occur by the Specified Completion Date.
Design-Builder recognizes that the City will incur significant internal and external costs (damages) as a result of any delay by the Design-Builder completing the required Work by the Substantial Completion Date and completing all Work by the Specified Completion Date.
If the Contract is terminated according to Section 16.a. and if the Work has not been completed by other means on or before the Specified Completion Date, liquidated damages shall be assessed against the Design-Builder for the duration of time reasonably required to complete the work.
ADD the following: Legal Holiday – ADD the following: Limited Notice to Proceed – ADD the following: Notice to Proceed – REPLACE with the following: Owner – Add the following: Owner’s Project Criteria – ADD the following: Owner’s Representative – ADD the following: Schedule of Values – ADD the following Specified Completion Date – ADD the following: The date of final completion and final acceptance.
The Contractor’s proposed Progress Schedule may indicate a completion date in advance of the Contract Specified Completion Date; however, the Department will not be liable in any way for the Contractor’s failure to complete the project prior to the Contract Specified Completion Date.
Prior to the Specified Completion Date, continued work on any Project shall be suspended as a result of the occurrence of an Event of Force Majeure for a period of one hundred eighty (180) or more consecutive days.