RLFC definition

RLFC means that all of the following have occurred with respect to Train 4: (i) Contractor has achieved and maintained RFSU for Train 4; (ii) the LNG Storage Tank has been successfully cooled down and is operating normally with LNG stored in such tank; (iii)
RLFC means that all of the following have occurred with respect to Train 4: (i) Contractor has achieved and maintained RFSU for Train 4;
RLFC means that LNG is ready for delivery to, and capable of being delivered to and loaded into, the LNG storage tank. In accordance with Sections 13.1A and 13.1.B of the EPC Agreement, if Substantial Completion occurs after the Guaranteed Substantial Completion Date (as adjusted by Change Order), for Train 3, Contractor shall pay to Owner Substantial Completion Delay Liquidated Damages in the amounts set forth in this Attachment E for each Day, or portion thereof, of delay until Substantial Completion occurs for Train 3, subject to the limitations in Section 20.2 of the EPC Agreement, provided that if Substantial Completion occurs within [***] ([***]) Days following the Guaranteed Substantial Completion Date (as adjusted by Change Order), for Train 3 (the “Grace Period”), then Contractor shall not be required to pay any Substantial Completion Delay Liquidated Damages for Train 3. If Substantial Completion occurs after the end of the Grace Period (i.e., [***] ([***]) Days (or later) after the Guaranteed Substantial Completion Date (as adjusted by Change Order), for Train 3), then Contractor shall pay to Owner Substantial Completion Delay Liquidated Damages in the amounts set forth in this Attachment E for each Day of delay during the Grace Period and thereafter. Contractor shall pay to Owner Substantial Completion Delay Liquidated Damages in accordance with Sections 13.1 and 13.2 of the EPC Agreement and this Attachment E. [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] More than [***] Days after the Guaranteed Substantial Completion Date $[***] [***]. KEY PERSONNEL AND CONTRACTOR’S ORGANIZATION The persons named in the table below, in accordance with Section 2.2A of the Agreement, are designated by Contractor and approved by Owner as Key Personnel. Key Personnel shall be assigned full time to the Work for the entire duration of the Project unless otherwise specified in this Attachment F. Without limiting the requirements of the Agreement, before any Key Personnel are assigned to the Project, the full names and 1-2 page résumés of nominated Key Personnel shall be provided to and approved by Owner. [***]. Replacements of any Key Personn...

Examples of RLFC in a sentence

  • Contractor shall provide Owner with monthly written notices updating its LNG production plan until [***] ([***]) months prior to RLFC and then weekly thereafter, provided, however, such written notices shall not require Owner to reschedule any LNG Tankers.

  • Contractor has caused this RLFC Certificate to be duly executed and delivered as of the date first written above.

  • Owner shall cause its Affiliate to cool down those portions of the Phase 1 Facilities that have achieved substantial completion necessary for Contractor to achieve RLFC and Substantial Completion.

  • Contractor certifies that all requirements under the Agreement for RLFC with respect to Train 4 were achieved on , 20 .

  • At least [***] ([***]) months prior to RLFC of each Train, Contractor shall prepare and provide Owner with Contractor’s LNG production plan, prepared by Contractor using GECP, detailing Contractor’s estimated production of LNG prior to Substantial Completion of each Train, including the dates and volumes of LNG to be produced and the dates in which it forecasts that such LNG would need to be removed from the LNG Storage Tanks to allow for such LNG production.

  • At least [***] ([***]) months prior to RLFC, Contractor shall prepare and provide Owner with Contractor’s LNG production plan, prepared by Contractor using GECP, detailing Contractor’s estimated production of LNG prior to Substantial Completion, including the dates and volumes of LNG to be produced and the dates in which it forecasts that such LNG would need to be removed from the LNG Storage Tank to allow for such LNG production.

  • If Owner does not agree that RFFGI, RFSU, RLFC, or Substantial Completion has occurred (as the case may be), then Owner shall state the basis for its rejection in reasonable detail in a notice provided to Contractor.

  • In connection with Train 4, Contractor shall give its best estimate of when natural gas feed is required to produce the LNG necessary to achieve RLFC of Train 4.

  • On or prior to thirty (30) Days prior to RLFC of Train 1, Owner shall procure and maintain stevedores/wharfingers liability consistent with prudent practices associated with the operation of the Facility and its dock facilities with minimum limits of [US$300,000,000] per occurrence and in the aggregate (which such limits may be met using a stevedores/wharfingers excess liability policy).

  • Contractor shall comply with all requirements for RLFC for Train 4 set forth in this Agreement, including those set forth in Attachment A and Attachment M.


More Definitions of RLFC

RLFC means that LNG is ready for delivery to, and capable of being delivered to and loaded into, the LNG storage tank. Attached hereto in Schedule E-1A is a level 1 schedule for Trains 1 and 2, and a level 1 schedule for Train 3. [***] [***] In accordance with Sections 13.1A and 13.1.B of the EPC Agreement, if Substantial Completion occurs after the Guaranteed Substantial Completion Date (as adjusted by Change Order), for the applicable Train, Contractor shall pay to Owner Substantial Completion Delay Liquidated Damages in the amounts set forth in this Attachment E for each Day, or portion thereof, of delay until Substantial Completion occurs for the applicable Train, subject to the limitations in Section 20.2 of the EPC Agreement. [***] Days after the Guaranteed Substantial Completion Date $[***] [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] [***] to [***] Days after the Guaranteed Substantial Completion Date $[***] More than [***] Days after the Guaranteed Substantial Completion Date $[***] [***].
RLFC means that all of the following have occurred with respect to the applicable Train: (i) Contractor has achieved and maintained RFSU for such Train; (ii) the applicable LNG Storage Tank(s) designated to be completed as part of such Train have been successfully cooled down and is operating normally with LNG stored in such tank(s); (iii) such Train has liquefied natural gas into LNG meeting all specifications and requirements of this Agreement (other than the Minimum Acceptance Criteria and Performance Guarantees) and successfully transferred and stored such LNG into the applicable LNG Storage Tank(s); (iv) the LNG Storage Tank(s) and all LNG loading and unloading lines (and equipment and systems related thereto) necessary for transfer of LNG from such LNG Storage Tank(s) to the loading dock have been cooled down and filled with LNG while remaining at cryogenic temperatures via circulation to the LNG berth and are ready for transfer of LNG to an LNG Tanker and for return of vapor and boil-off gas to the LNG tanks, and the loading dock or berth have successfully passed and Owner has approved the pre-LNG arrived berth readiness review; (v) LNG is ready for delivery to, and capable of being delivered to and loaded into, an LNG Tanker via the loading dock; (vi) Contractor has delivered to Owner an RLFC Certificate for such Train in the form of Schedule L-4 and Owner has accepted such certificate by signing such certificate; and (vii) performance by Contractor of all other obligations required under this Agreement for RLFC of such Train.