Examples of Required Substantial Completion Date in a sentence
Accordingly, notwithstanding anything in this Clause E5, even if conditions exist which would otherwise be an excusable delay hereunder to Contractor’s performance of the Work, Contractor may only be entitled to seek an extension of the Contract Time (for any Schedule Milestones or the Required Substantial Completion Date) only to the extent that such excusable delay is proven to the satisfaction of Princeton University in its discretion to demonstrably impact the critical path of the Project Schedule.
Notwithstanding the preceding or any approvals by Princeton University of any Updated Project Schedules or anything in this Contract to the contrary, any change to the Required Substantial Completion Date or any of the Schedule Milestones shall only be pursuant to a Change Order signed by Princeton University.
Updated Project Schedule(s) shall be subject to Princeton University’s written approval, shall not change the previously established Required Substantial Completion Date or any of the Schedule Milestones, and shall not be binding upon Princeton University in any manner unless or until Princeton University has approved such Updated Project Schedule, subject to any qualifications in such approval and all other terms of this Contract.
If no such agreement is reached, Contractor shall give notice to Architect and Owner of its objection to the change, if any, in the Contract Sum, Required Substantial Completion Date and/or Required Final Completion Date proposed in the Change Directive within five (5) business days after receipt of the Change Directive.
Learning phrase representations using RNN encoder-decoder for statistical machine translation.
An equitable adjustment by Agreed Change shall be made for increases in the Contract Sum, Required Substantial Completion Date and Required Final Completion Date on account of any such suspension, delay or interruption.
In case of a termination of a portion of the Work, Owner will execute an Agreed Change making any required adjustment to the Required Substantial Completion Date, Required Final Completion Date and/or the Contract Sum necessitated by such termination.
Contractor acknowledges that a delay in any one portion of the Project or in any Work sequence or any other aspect of the Work does not necessarily entitle Contractor to a delay in, or a delay of equal duration in, completion of the entire Project, or a delay that materially and adversely affects the Required Substantial Completion Date.
Such agreement shall be effective immediately and shall be an “ Agreed Change,” which term, as used herein, shall mean any change in the Work as to which Contractor and Owner have agreed as any changes in the Contract Sum, the Required Substantial Completion Date and the Required Final Completion Date.
Owner may, without issuing a Change Directive, issue a request for the effect of a proposed change by a “ Proposed Change.” Any Proposed Change shall be in the form of a Change Directive, except that, instead of setting forth Owner’s proposal for the change, if any, in the Contract Sum, Required Substantial Completion Date or Required Final Completion Date, the same shall request a proposal from Contractor therefor.