Requested Service Project definition
Examples of Requested Service Project in a sentence
The Study Team shall collaboratively develop a Proposed Requested Service Project.
The Board shall review and may approve the Study Team’s determination that each Recommended Requested Service Project (i) serves its underlying transmission service or interconnection request and (ii) does not result in any unmitigated Material Adverse Impacts on any transmission system; provided that no Recommended Requested Service Project shall be included in any Plan unless the requestor and all Affected Persons agree upon such Requested Service Project.
ColumbiaGrid may allocate costs in a Facilities Agreement to a ▇▇▇▇ that has a Need during the Planning Horizon that is met by the Requested Service Project; provided that ColumbiaGrid shall not allocate costs in an amount that exceeds the cost that would have been incurred by such ▇▇▇▇ had it met its Need with a separate EOP.
A Requested Service Project in a Biennial Plan (or Plan Update) shall include a Plan of Service, estimated costs, transmission capacity allocation, cost and ownership allocation, and schedule.
A Proposed Requested Service Project is ready for inclusion in a Draft Plan when (i) all of the Affected Persons identified by ColumbiaGrid that have actively participated in a related Study Team have agreed to each element of such Requested Service Project, and (ii) the Study Team has confirmed that such Project meets the request and has appropriately mitigated Material Adverse Impacts resulting from such Project on any transmission systems, and (iii) the requestor has agreed to pursue the Project.
If there is an accompanying Need which can be delayed or eliminated by the Requested Service Project within the Planning Horizon, ColumbiaGrid shall endeavor to make an equitable allocation of costs of such Staff- Recommended Requested Service Project based upon the affected ▇▇▇▇’▇ OATT requirements and the delay or elimination of the Need.
The Staff may present more than one Recommended Requested Service Project for the Board to select from.
In the event that such Affected Persons do not reach agreement on a Requested Service Project in whole or in part within a reasonable time, Staff shall make a recommendation for any unresolved element(s) and may, as the Staff finds appropriate, present fully-developed alternatives for the Board’s consideration.
If the Staff-Recommended Requested Service Project is approved by the Board and agreed upon by the requestor and all Affected Persons it will be included in the Draft Plan.
A Staff- Recommended Requested Service Project shall not have any unmitigated Material Adverse Impacts resulting from such Project on any transmission systems.