Each Project Status Schedule Update shall indicate the overall completion percentage of the Project.
The Project Status Schedule Update shall include a schedule narrative report which describes the status of the Project in detail.
No changes in activity durations, calendar assignments, logic ties, or constraints will be allowed in the Project Status Schedule Update without the written approval of TxDOT.
Developer shall submit a single hard copy of the Project Status Schedule Update in a single copy in full- size color plot sheets along with a backup disk of the schedule in electronic format.
Each Project Status Schedule Update shall accurately reflect all activities completed as of the effective date of the update schedule.
Each Project Status Schedule Update shall accurately reflect the status of all activities as of the effective date of the updated Project Baseline Schedule.
Upon completion of the Punch List, the Design-Build Contractor will submit the Project Status Schedule Update identified as the “as-built schedule”.
Cost information shall be included with Design-Build Contractor’s first monthly Project Status Schedule Update.
Each time impact analysis shall include a fragmentary network demonstrating how the Design-Build Contractor proposes to incorporate the change, delay, or Design-Build Contractor request into the current Project Status Schedule Update.
If the Work is delayed on any Critical Path item for a period which exceeds the greater of either thirty (30) Days in the aggregate or that number of days in the aggregate equal to five (5) percent of the days remaining until Final Acceptance for the last Project Segment, the next Project Status Schedule Update shall include a recovery schedule demonstrating the proposed plan to regain lost Project Schedule progress and to achieve Final Acceptance of the last Project Segment by the specified date.