Preliminary Acceptance Test definition
Examples of Preliminary Acceptance Test in a sentence
E.11.1. When it has been demonstrated to MIMOS's satisfaction that the Equipment and/or Software has successfully met the requirements of the schedule of Preliminary Acceptance Tests, the Contractor shall provide MIMOS all applicable handover documentation, including without limitation site layout, Equipment layout and network design of the Equipment and Software supplied as well as the Preliminary Acceptance Test results (collectively, “Handover Documents”).
The Seller/System Integrator and the End-user shall mutually execute the certificate of Preliminary Acceptance within three Business Days after the completion of the Preliminary Acceptance Test of the Contracted Equipment.
If the Acceptance Tests have been satisfactorily completed, the Borrower shall deliver to the Administrative Agent and the Loan Insurer the Preliminary Acceptance Test Results and the Independent Engineer will, upon a thorough review of such Preliminary Acceptance Test Results, certify in writing to the Administrative Agent, the Lenders and the Loan Insurer, within five (5) Business Days of the receipt of such Preliminary Acceptance Test Results, the satisfactory achievement of the Acceptance Tests.
Within 15 days prior to the commencement of the Preliminary Acceptance Test, the Seller/System Integrator should confirm in writing with the End-user the date of Preliminary Acceptance Test and submit the testing scheme and related documents consistent with the test procedures and standards of Preliminary Acceptance Test as set out in Appendix 6 attached hereto.
All the cost incurred in solving such problem and resuming the Preliminary Acceptance Test shall be borne by the Seller/System Integrator.
If, due to reasons not attributable to the End-user, the Preliminary Acceptance Test fails to come up to all the indexes and standards as set out in Appendix 1 of this Contract, the Seller shall eliminate the existent problem within 15 business days and resume the Preliminary Acceptance Test.
The Seller and the End-user shall mutually execute the certificate of Preliminary Acceptance within five Business Days after the completion of the Preliminary Acceptance Test of the Contracted Equipment.
DBSI shall be preliminary notified 10 calendar days prior to the beginning of the Preliminary Acceptance Test activity, and will then have the opportunity to decide upon its participation.
If, due to reasons not attributable to the End-user, the Preliminary Acceptance Test fails to come up to all the indexes and standards as set out in Appendix 1 of this Equipment Contract, the Seller/System Integrator shall eliminate the existent problem within 15 business days and resume the Preliminary Acceptance Test.
The aforementioned payment shall not relieve the Seller from its obligation to complete the Preliminary Acceptance Test of the Contracted Equipment and to get a pass in such test.