Post Completion Works definition
Examples of Post Completion Works in a sentence
Template drafting has been provided here for Post Completion Works, to be used where relevant.
Any items of equipment redundant within the Existing School not removed by the Authority in the agreed period of [two] weeks as detailed within paragraph 15.3 (Removal of existing school items of equipment) detailed below, will be removed by the Contractor during the Post Completion Works Phase.
Project Co shall procure that the provision of the Services commences on the Actual Completion Date [for a Facility] [and in respect of the Post Completion Works Areas, the [relevant] Actual Post Completion Works Date] [for a Facility].
For the avoidance of doubt clause 20.4.1 and clause 20.4.2 shall be the Authority’s sole remedy in connection with any delays to the completion of the Post Completion Works and the Authority shall not be entitled to levy any Deductions under Schedule 6 (Payment Mechanism) in relation to any Areas which are subject to Post Completion Works prior to the Post Completion Works Acceptance Date.
The Landlord will procure that the Date of Practical Completion occurs by the Target Date except for the Post Completion Works.
Therefore, where demolition and/or landscaping are to occur after the final Services Availability Date, the definition should refer to the Post Completion Works Acceptance Date.
A final account shall be required for [each of] the [Main] Works [(the "Main Works Final Account")] [and the Post Completion Works (the "Post Completion Works Final Account"), each] a "Statement of Final Account".
Independent Certifier shall within five (5) Business Days of the issue of the relevant ICT Handover Acceptance Certificate, Acceptance Certificate [or Post Completion Works Acceptance Certificate] issue to the Contractor and the Authority a list of the relevant Snagging Items for that School (the Snagging List).
Contractor's sole remedy in relation to any Compensation Event in respect of the Works at any Site that occurs prior to the applicable Longstop Date [and the Post Completion Works at any Site] shall be the operation of clause 16.5 (Effect of a Compensation Event).
Programme[s] [in respect of the Main Works and the Post Completion Works] shall be in accordance with the [relevant] Outline Commissioning Programme and shall impose no greater or more onerous obligations on the Authority than those set out in the [relevant] Outline Commissioning Programme (unless otherwise agreed by the Authority in its absolute discretion).