Phase Substantial Completion definition

Phase Substantial Completion with respect to Phase 1, all of the conditions set forth in Section 15.1.1 have been satisfied (or have been waived by Owner), and, with respect to all Phases other than Phase 1, all of the conditions set forth in Section 15.1.2 have been satisfied (or have been waived by Owner) with respect to each of the Blocks comprising such Phase (including that all of the Blocks comprising such Phase have achieved Substantial Completion);
Phase Substantial Completion means, with respect to each Phase, the satisfaction (or waiver by Owner) of the requirements set forth in Section 15.2 with respect to such Phase.

Examples of Phase Substantial Completion in a sentence

  • The CPM Schedule shall represent Contractor's best judgment as to how it shall complete the Work in compliance with the Schedule Milestones including the Phase Substantial Completion Guaranteed Dates, the PV Power Plant Substantial Completion Guaranteed Date, and the Final Completion Guaranteed Date.

  • Landlord shall complete Punchlist Items after the applicable Phase Substantial Completion Date.

  • Following commencement of any Work, Developer shall diligently pursue in good faith the completion of the Work so that Substantial Completion of the Project Phase is achieved no later than the Project Phase Substantial Completion Date, subject to extension as provided in this Agreement.

  • If Contractor fails to achieve the Minimum Performance Guarantee for any Phase, Contractor shall continue seeking to achieve at least the Minimum Performance Guarantee for such Phase, and Contractor must continue to perform the Work until Contractor achieves Phase Substantial Completion for such Phase (it being understood that achievement of the Minimum Performance Guarantee is an express condition of Phase Substantial Completion).

  • Commencing no later than forty-five (45) days prior to the anticipated Phase Substantial Completion Date for Phase 1 and, again, 45 days prior to the anticipated PV Power Plant Substantial Completion, Contractor shall, or where applicable, shall cause the Subcontractors to, train designated Operating Personnel, including Owner's operations supervision employees in accordance with the training program set forth in Exhibit E.

  • If Contractor elects to attempt to satisfy the applicable Performance Guarantee as provided in Section 16.6.1(b) after the Phase Substantial Completion Date or PV Power Plant Substantial Completion Date, as applicable, Contractor shall submit a Remedial Plan to Owner, which shall specify the corrective actions Contractor will take and the commencement date of such corrective action, for Owner's approval, which shall not be unreasonably withheld.

  • Contractor shall exercise either option provided in this Section 16.6.1 by delivery of Notice to Owner not later than ten (10) days after the Phase Substantial Completion Date or PV Power Plant Substantial Completion Date, as applicable.

  • Owner agrees that if Contractor achieves Phase Substantial Completion for a Phase prior to with respect to ▇▇▇▇▇ ▇, ***, with respect to Phase 2 or Phase 4, ***, with respect to ▇▇▇▇▇ ▇, ***, or achieves the PV Power Plant Substantial Completion prior to the PV Power Plant Substantial Completion Guaranteed Date, Contractor shall be entitled to a bonus payment (“Bonus Payment”) from Owner in the amount of $***.

  • Upon completion thereof, Project Co may give a further Substantial Completion Notice and Sections 25.2(c) to (e), inclusive, shall be repeated until the Phase Substantial Completion Certificate or Substantial Completion Certificate has been issued.

  • Owner's review of the CPM Schedule shall not relieve Contractor of any obligations for the performance of the Work, change the Phase Substantial Completion Guaranteed Dates, the PV Power Plant Substantial Completion Guaranteed Dates, or the Final Completion Guaranteed Dates.