Permissible Delays definition
Examples of Permissible Delays in a sentence
Each Progress Report shall also clearly describe any slippage in progress; any event(s) that may cause delay (whether alleged to be Permissible Delays or otherwise) in the punctual delivery of the Vessel; the estimated period(s) of delay attributable to such event(s); the Builder’s proposals on avoiding and/or mitigating the effects of such event(s) on the punctual delivery of the Vessel.
If the delay in delivery of the VESSEL should continue for a period of hundred and fifty (150) days from the thirty-first (31st) day after the Delivery Date (adjusted for Permissible Delays), then in such event, and after such period has expired, the BUYER may at its option cancel this Contract in accordance with the provisions of Article VIII hereof.
If the total accumulated time of all delays, excluding Permissible Delays, amounts to Three Hundred and Sixty (360) days or more, then, in such event, the BUYER may cancel this Contract in accordance with the provisions of Article III hereof.
Delays on account of such causes as specified in Clause 1 of this ARTICLE VIII and in ARTICLE IV, Clause 4(i)(2)), ARTICLE V, ARTICLE VI, ARTICLE XI, ARTICLE XII, ARTICLE XVII and ARTICLE XVI shall be understood to be Permissible Delays and are to be distinguished from unauthorized delays on account of which the Contract Price is subject to adjustment and/or the Contract is subject to rescission as provided for respectively in Article III and Article X hereof.
Acceptance of any delays defined as Permissible Delays, including but not limited to Rain Delays, or Force Majeure shall not be unreasonably withheld by the Purchaser.
If any default by BUYER under Paragraphs (a), (b) or (c) above necessarily and actually causes delays in either the construction of the VESSEL or any performance required as a prerequisite to delivery of the VESSEL, such delays shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2.
Any such alterations in the Delivery Date as may be mutually agreed in writing shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2.
Any delay of the Tests and Trials caused by such unfavorable weather conditions shall operate to postpone the Delivery Date by the period of delay involved and such delay shall be understood to constitute Permissible Delays as contemplated in Article III, Paragraph 2.
If OWNER's failure to timely deliver OWNER Furnished Equipment to BUILDER's Shipyard directly causes any delays in the BUILDER's Construction Schedule, then such delays shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2, and the Delivery Date shall be extended by the equivalent number of days of delay in delivery of such OWNER Furnished Equipment to BUILDER's Shipyard.
Any alterations in the Delivery Date as may be mutually agreed in writing as a result of such changes shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2.