Permissible Delays definition

Permissible Delays means delays to the construction and/or delivery of the Vessel and which entitle the Builder to extend the Delivery Date in accordance with Clause 34 (Permissible Delays).

Examples of Permissible Delays in a sentence

  • Each Progress Report shall also clearly describe any slippage in progress; any event(s) that may cause delay (whether alleged to be Permissible Delays or otherwise) in the punctual delivery of the Vessel; the estimated period(s) of delay attributable to such event(s); the Builder’s proposals on avoiding and/or mitigating the effects of such event(s) on the punctual delivery of the Vessel.

  • If the delay in delivery of the VESSEL should continue for a period of hundred and fifty (150) days from the thirty-first (31st) day after the Delivery Date (adjusted for Permissible Delays), then in such event, and after such period has expired, the BUYER may at its option cancel this Contract in accordance with the provisions of Article VIII hereof.

  • If the total accumulated time of all delays, excluding Permissible Delays, amounts to Three Hundred and Sixty (360) days or more, then, in such event, the BUYER may cancel this Contract in accordance with the provisions of Article III hereof.

  • Delays on account of such causes as specified in Clause 1 of this ARTICLE VIII and in ARTICLE IV, Clause 4(i)(2)), ARTICLE V, ARTICLE VI, ARTICLE XI, ARTICLE XII, ARTICLE XVII and ARTICLE XVI shall be understood to be Permissible Delays and are to be distinguished from unauthorized delays on account of which the Contract Price is subject to adjustment and/or the Contract is subject to rescission as provided for respectively in Article III and Article X hereof.

  • Acceptance of any delays defined as Permissible Delays, including but not limited to Rain Delays, or Force Majeure shall not be unreasonably withheld by the Purchaser.

  • If any default by BUYER under Paragraphs (a), (b) or (c) above necessarily and actually causes delays in either the construction of the VESSEL or any performance required as a prerequisite to delivery of the VESSEL, such delays shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2.

  • Any such alterations in the Delivery Date as may be mutually agreed in writing shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2.

  • Any delay of the Tests and Trials caused by such unfavorable weather conditions shall operate to postpone the Delivery Date by the period of delay involved and such delay shall be understood to constitute Permissible Delays as contemplated in Article III, Paragraph 2.

  • If OWNER's failure to timely deliver OWNER Furnished Equipment to BUILDER's Shipyard directly causes any delays in the BUILDER's Construction Schedule, then such delays shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2, and the Delivery Date shall be extended by the equivalent number of days of delay in delivery of such OWNER Furnished Equipment to BUILDER's Shipyard.

  • Any alterations in the Delivery Date as may be mutually agreed in writing as a result of such changes shall be understood to be Permissible Delays as contemplated by Article III, Paragraph 2.

Related to Permissible Delays

  • Excusable Delays means delays due to acts of terrorism, acts of war or civil insurrection, strikes, riots, floods, earthquakes, fires, tornadoes, casualties, acts of God, labor disputes, governmental restrictions or priorities, embargoes, national or regional material shortages, failure to obtain regulatory approval from any Federal or State regulatory body, unforeseen site conditions, material litigation by parties other than the Parties not caused by the Parties’ failure to perform, or any other condition or circumstances beyond the reasonable or foreseeable control of the applicable party using reasonable diligence to overcome which prevents such party from performing its specific duties or obligation hereunder in a timely manner.

  • Force Majeure Delays means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.

  • Excusable Delay means a delay due to acts of God, governmental restrictions, stays, judgments, orders, decrees, enemy actions, civil commotion, fire, casualty, strikes, work stoppages, shortages of labor or materials or other causes beyond the reasonable control of Borrower, but lack of funds in and of itself shall not be deemed a cause beyond the control of Borrower.

  • Unavoidable Delays means delays due to any of the following, and only the following, (provided that such delay is beyond Construction Manager’s reasonable control): war, insurrection, civil commotion, strikes, slowdowns, lock outs, riots, flood, earthquakes, fires, casualties, acts of God, acts of a public enemy, acts of terrorism, epidemics, quarantine restrictions, freight embargoes, lack of transportation, governmental moratoriums, unusually severe or abnormal weather conditions, failure of utilities, or a court order which causes a delay (unless resulting from a wrongful act of Construction Manager). In no event shall the application to Construction Manager of any applicable law, regulation, rule or other governmental requirement constitute an Unavoidable Delay. Contractor shall use reasonable good faith efforts to notify Owner not later than five (5) days after Construction Manager knows of the occurrence of an Unavoidable Delay. An extension of time for an Unavoidable Delay shall only be for the period of the Unavoidable Delay, which period shall commence to run from the time of the commencement of the cause of the Unavoidable Delay.

  • Force Majeure Delay means with respect to the Servicer, any cause or event which is beyond the control and not due to the negligence of the Servicer, which delays, prevents or prohibits such Person’s delivery of the reports required to be delivered or the performance of any other duty or obligation of the Servicer under the Indenture, as the case may be, including, without limitation, computer, electrical and mechanical failures, acts of God or the elements and fire; provided, that no such cause or event shall be deemed to be a Force Majeure Delay unless the Servicer shall have given the Indenture Trustee written notice thereof as soon as practicable after the beginning of such delay.