Performance Verification Test definition
Examples of Performance Verification Test in a sentence
The Contractor shall develop and deliver a Test and Evaluation Program Plan (▇▇▇▇) (CDRL A028) to include the following: Performance Verification Test Procedures - verifies that the performance requirements of the complete equipment satisfies the CIDs requirements.
The Contractor shall develop and deliver a Test and Evaluation Program Plan (▇▇▇▇) (CDRL A029) to include the following: Performance Verification Test Procedures - verifies that the performance requirements of the complete equipment satisfies the CIDs requirements.
Bailment Period: From Effective Date of the order through 15 calendar days after either Qualification Test or Performance Verification Test is completed, or later if agreed to by the parties.
If the System is unable to pass the Performance Verification Test within sixty (60) days after we begin receiving data and after Omnidian has worked in good faith with your Contractor to remedy any deficiencies that might keep the System from passing, this failure will be deemed a Change to the System pursuant to Section II.A of this Agreement and the procedures specified therein will apply.
If you decline the cost of the Performance Verification Test, Omnidian will retain the right, at its sole discretion, (a) to continue this Agreement unchanged, (b) terminate this Agreement pursuant to Section III.E of this Agreement and issue a refund pursuant to Section III.J or (c) to modify this Agreement to reflect the changes to the System, to alter the Prepaid and/or Monthly Subscription Cost of this Agreement and, if necessary, to adjust the Guaranteed Year 1 Annual Energy.
We will make commercially reasonable efforts to complete the Performance Verification Test within the first thirty (30) days after we begin receiving data.
LAWA ACAMS O&M Provider is responsible for performing all testing, including Installation Performance Verification Test and Commissioning.
In the event of a performance or installation deficiency, Omnidian may, in its sole discretion, increase the time period to complete the Performance Verification Test.
The Performance Verification Test shall demonstrate the throughput and response time of the PACKAGE and DIAGNOSTICS.
If you agree to pay for the costs of such test, Omnidian will issue an invoice or ▇▇▇▇ for such costs after performance of the additional Performance Verification Test.