New Substation definition

New Substation shall have the meaning set forth in Section 5(b)(2)(ii)(j).

Examples of New Substation in a sentence

  • Within ninety (90) Days of the energization of the New Substation and Tap Line the Company shall perform an overall reconciliation of the Actual Costs to the costs previously invoiced to, and paid to Company by, CHURCHVILLE for the Work, and the Company shall provide a final invoice for an amount due to the Company, or credit owed to CHURCHVILLE, as the case may be.

  • Functional testing of the New Substation, Tap Line and line switch.

  • May 1, 2011- CHURCHVILLE grants all permits and easements to Company in form and substance satisfactory to Company Completed - CHURCHVILLE completes New Substation.

  • Inspect and approve CHURCHVILLE’s construction of + or – 420 feet of 34.5 kV Tap line from the New Substation to Company’s existing 34.5 kV sub transmission line 201 (the “Tap Line”) as constructed prior to final connection.

  • Company shall bear no risk of loss or damage of any kind or nature whatsoever with respect to the cost of all packaging and shipment of equipment and material to the Site, of all unloading, storage, protection and installation of equipment and material at the Site, and of any insurance on the equipment prior to energization of the Tap Line and the New Substation, regardless of whether title has passed to the Company.

  • The Lessee shall perform all installation, testing and commissioning of equipment required for the operation of the New Substation.

  • Additionally, there may be constructed a redundant line feed (or underground duct facilities) in an underground area on the Project site and the River House Housing Project site, running northerly from Point Street, under the main driveway for the River House Housing Project site, then west along South Street and then northerly along the northwest portion of the Project site (parallel to Eddy Street), to a point of connection into the New Substation (the “Redundant Line Feed”).

  • Also, pursuant to the NGRID Agreement, NGRID will bury the above-ground power transmission lines on the Project site and the River House Housing Project site (and remove the associated towers) to an approximate location from Point Street, generally running northerly along the eastern boundary of each such site, in, under or near the planned pedestrian walkway along the Providence River to a point of connection into the New Substation (the “Primary Line Feed”).

  • To facilitate in making its competitive bid to BPC, POWERGRID has undertaken Invitation for Bids (IFB) process for 400kV AIS (New) Substation Package -SS-17T for (i) Establishment of 4x500MVA, 400/220 kV Pooling Station near Dhule along with 2x125 MVAr (420kV) Bus Reactor and (ii) Extn.