Materiality Trigger definition
Examples of Materiality Trigger in a sentence
Where additional Developer Capacity allocated in Part 1 exceeds the Materiality Trigger, or for a single Relevant Embedded Medium Power Station or a single Embedded Large Power Station, The Company will need to carry out further studies to assess the impact on the National Electricity Transmission System.
The User must initiate this process within 10 working days of exceeding the Materiality Trigger by the submission of agreed updated technical data in the form of a Modification Application.
Where the User provides a Modification Application and the technical data within 10- working days of the Materiality Trigger being breached and The Company has confirmed the submission (including the agreed updated technical data) to be competent, the User may continue to make offers to new Relevant Embedded Power Stations based on the existing Technical Limitations until further notice by The Company.
Total Developer Capacity [ ]MW Subject to Cancellation Charge in accordance with CUSC Section 15 User Commitment Methodology Materiality Trigger [ ]MW Once the Materiality Trigger is breached, the Materiality Trigger Process (as documented in Schedule 2) is required to be followed and a Modification Application submitted within 10 working days in order to continue making offers on the transmission terms and conditions set out in this agreement.
For the avoidance of doubt The Company will provide details of the Site Specific Requirements, Interim Restrictions on Availability and applicable Construction Works that the User must apply to any future Relevant Embedded Power Station applications within the Materiality Trigger and this will be set out at the bottom of Part 1.
The Materiality Trigger of the donor GSP should be lowered and the recipient raised by the same amount with both GSP Appendix G updates submitted together.
Where requirements at the Connection Site exceed the Total MWs set by a wider system limitation rather than the capacity at the Connection Site it may be possible to transfer Developer Capacity by reducing the Materiality Trigger from another connection site within the wider system limitation group.
The Materiality Trigger should not be lowered below the total Developer Capacity on Table 1.
Generator Technology See Note There is no limit on technology change within this GSP Materiality Trigger.
Either not confirm the impact upon Relevant Embedded Power Stations or confirms there is no impact upon Relevant Embedded Power Stations, the Total MWs and/or Materiality Trigger shall be reduced.