Major Change Order definition
Examples of Major Change Order in a sentence
The Parties shall execute any necessary amendment to this Contract in accordance with Article 42 (Amendments) within thirty (30) days of Customer’s written agreement to a Major Change Order Proposal submitted by Boeing.
The Parties shall negotiate the terms contained in the Proposal, and upon the written agreement by Customer of the adjustments to be made to the Contract, Boeing shall immediately proceed with implementation of the Major Change Order.
This warranty shall expire one year after Preliminary Acceptance for a Satellite or upon Intentional Ignition, whichever comes first, unless the warranty is extended through a Major Change Order pursuant to Article 24.1 (Material Changes Requested by Customer) in connection with post-Delivery storage of a Satellite as contemplated under Article 34.4 (Storage Prices).
In the event Customer requests a Major Change Order, Boeing shall, within thirty (30) days of Customer’s request (or any longer period requested in good faith by Boeing, and reasonably granted in writing by Customer) submit to Customer a written proposal of the effect of such a change on the Firm Fixed Price, specification, Payment Plan, time required for performance and/or other affected terms and conditions (the “Proposal”).
If Landlord fails to approve or disapprove (with stated reasons) in writing the Change Order or Major Change Order within the period specified above, such Change Order shall be deemed approved by Landlord.
Once any Major Change Order that is subject to the City’s approval is approved or deemed approved by the City, PCL shall be permitted to enter into or approve such Major Change Order, on the condition that such Major Change Order is implemented substantially in accordance with the Change Order Documents delivered by PCL to the individual designated by the City pursuant to Section 4.04(b) with respect thereto.
Landlord agrees to approve or disapprove (with stated reasons) in writing any Change Order within two (2) Business Days after receipt of the Change Order and the revised Final Plans thereof, unless such Change Order is a Major Change Order.
Within ten (10) Business Days of its receipt of a request for approval of a Major Change Order, the non- requesting Party shall notify the requesting Party in writing of its approval or disapproval thereof, and, in the case of disapproval, shall provide a detailed reason of its disapproval of such Major Change Order.
Within five (5) Business Days after receipt by the individual designated by the City pursuant to Section 4.04(b) of all Change Order Documents related to any Major Change Order subject to the City’s approval, the City shall deliver written notice to PCL either approving such Major Change Order or disapproving such Major Change Order and specifying the reasons for such disapproval.
As used herein, the term "Major Change Order" shall mean a Change Order for a Change that (a) would affect Building systems or the structure of the Building, (b) would affect the exterior appearance of the Building, or (c) would cost in excess of Ten Thousand Dollars ($10,000.00).