Examples of IUSA in a sentence
The term of the network operating agreement must be for a period which is at least equal to the term of the longest connection agreement of a member of the initial identified user group for the third party IUSA.
Before commissioning, the Primary Transmission Network Service Provider must ensure that contestable IUSA components are built to the standards specified in the functional specification provided under clause 5.3.3(b)(9) and the Connection Applicant for the identified user shared asset must provide access to the Primary Transmission Network Service Provider to make inspections, and agree to such tests, as is reasonably required for that purpose.
A person must not commission, or permit the commissioning of, a third party IUSA unless there is a network operating agreement between the owner of that third party IUSA and the Primary Transmission Network Service Provider.NoteThis clause is classified as a civil penalty provision under the National Electricity (South Australia) Regulations.
To the extent that any components of an identified user shared asset do not satisfy the criteria set out in paragraph (c) (“non-contestable IUSA components”), the Primary Transmission Network Service Provider must negotiate under rule 5.3 to undertake the detailed design, construction and ownership of the non-contestable IUSA components as a negotiated transmission service.
NoteParties may seek the advice of an Independent Engineer under rule 5.4 if the parties cannot agree on whether a component of an identified user shared asset based on the criteria under subparagraph (c)(1) and (2) is a contestable IUSA component or a non-contestable IUSA component.
See clause 5A.A.1. contestable IUSA componentsThose components of the identified user shared asset that satisfy the criteria set out in clause 5.2A.4(c).
IUSA assets with capital costs less than $10 million are negotiated services that can only be provided by Powerlink.
IUSA assets with capital costs above $10 million are non-regulated services.
A person must not commission, or permit the commissioning of, a third party IUSA unless there is a network operating agreement between the owner of that third party IUSA and the Primary Transmission Network Service Provider.
A person must not commission, or permit the commissioning of, a third party IUSA unless there is a network operating agreement between the owner of that third party IUSA and the Primary Transmission Network Service Provider.NoteThis paragraph is classified as a tier 2 civil penalty provision under the National Electricity (South Australia) Regulations.