IP Steam definition

IP Steam means the Adjusted IP Steam Output as such term is used in the EPC Agreement. x=7.4 y=20 "PJM Net Capability Verification Test" shall mean a semi-annual test conducted, in accordance with the Test Plan, to determine the Rated Capacity of the Facility. Each PJM Net Capability Verification Test shall be conducted on the date determined by Owner, but no later than June 30th, for the first such test during a Project Year and no later than December 31st for the second such test during a Project Year. One such test will be performed at PJM winter ambient temperature rating, and one such test will be performed at PJM summer ambient temperature rating. All test data will be taken at PJM ambient temperatures +/- 3 degrees F. The PJM Net Capability Verification Test will be conducted during a two-hour (2) period any time after the Facility has achieved steady state operation. The results of the PJM Net Capability Verification Test will consist of the average of three (3) data points, one at time zero, one at the end of the first hour and one at the end of the second hour. The Target Rated Capacity for the first Project Year will be determined from the results of the acceptance test to be performed in accordance with the EPC Agreement. The peak electric power rating and steam power augmentation capability of the equipment shall not be utilized in such determination.

Examples of IP Steam in a sentence

  • CLI and LCC shall mutually agree on the final engineering design (to the extent required to ensure compatibility between the CLI IP Steam Piping Systems and the LCC IP Steam Piping Systems) of, and the timing of the initial delivery of any steam to LCC through, the IP Steam Piping Systems, whether for purposes of start-up, testing or otherwise.

  • Contractor guarantees that the minimum average Adjusted IP Steam Output-NG, as demonstrated during the most recent Performance Test-NG shall be equal to or greater than 32,955 #s/hr as measured at the intermediate pressure steam outlet flow meter located directly downstream of the HRSG superheater.

  • CLI and LCC shall mutually agree when the IP Steam Piping Systems Commercial Operation Date has occurred.

  • CLI shall (a) design, engineer, procure, construct and install the CLI IP Steam Piping Systems in a manner consistent with Prudent Operator Standards and applicable Legal Requirements so that they are capable of meeting the IP Steam Piping Systems Commercial Operation Conditions by January 1, 2007, and (b) cause the Dry Low NOx Conversion on the remaining combustion turbines that form part of the CLI Facility to be completed by April 30, 2007.

  • Each Party shall provide the other Party with any information that the first Party may have that is reasonably required by the other Party in designing, engineering, procuring, constructing or installing its portion of the IP Steam Piping Systems.

  • UTILITIES The Business Amines ▇▇▇▇▇▇ Water Fire Water Potable Water Effluent HP Steam IP Steam LP Steam Condensate Nitrogen (by pipeline) ------------------------------------------------------------------------------------- 6.

  • Contractor agrees to pay, if a Performance Test has been conducted on the Facility on Fuel-LSFO, at a rate of One Hundred Forty Dollars ($140.00) for each lb of IP Steam that the Adjusted IP Steam Output of the Facility (as measured during the most recent Performance Test on Fuel-LSFO) is less than the IP Steam Guarantee-LSFO (the "Steam Output Liquidated Damages-LSFO (IP)").

  • Contractor agrees to pay, if a Performance Test has been conducted on the Facility on Fuel-NG, at a rate of One Hundred Forty Dollars ($140.00) for each lb of IP Steam that the Adjusted IP Steam Output of the Facility (as measured during the most recent Performance Test on Fuel-NG) is less than the IP Steam Guarantee-NG (the "Steam Output Liquidated Damages-NG (IP)").

  • LCC shall cause the LCC IP Steam Piping Systems to interconnect with the CLI IP Steam Piping Systems at the point determined according to Section 6.7.

  • LCC shall design, engineer, procure, construct and install the LCC IP Steam Piping Systems in a manner consistent with Prudent Operator Standards and applicable Legal Requirements so that they are capable of meeting the IP Steam Piping Systems Commercial Operation Conditions.