Interim Directed Change definition
Examples of Interim Directed Change in a sentence
Changes in the Work that are within the general scope of this Agreement shall be accomplished, without invalidating this Agreement, by Change Order and Interim Directed Change.
As the changed Work is performed, the Construction Manager shall submit its costs for such Work with its application for payment beginning with the next application for payment within thirty (30) Days of the issuance of the Interim Directed Change.
If an increase or decrease cannot be agreed to as set forth in subsections 9.3.1.1 and 9.3.1.2 above, and the Owner issues an Interim Directed Change, the cost of the change in the Work shall be determined by the reasonable actual expense incurred and savings realized in the performance of the Work resulting from the Change.
The Construction Manager shall not be obligated to perform changes in the Work that impact the GMP or the estimated Cost of the Work, Construction Manager's Fee, Date of Substantial Completion or Date of Final Completion until a Change Order has been executed or a written Interim Directed Change has been issued.
The Owner and the Construction Manager shall negotiate expeditiously and in good faith for appropriate adjustments, as applicable, to the GMP or the date of Substantial Completion or date of Final Completion arising out of an Interim Directed Change.
Otherwise, the Subcontractor shall separately submit its costs for the resulting change, beginning with its next regularly scheduled application for payment submitted after the issuance of the Interim Directed Change.
If such Interim Directed Change is issued as a result of the Owner's issuance of an Interim Directed Change, Construction Change Directive, or equivalent directive, then the applicable provisions of the prime agreement shall govern.
When the Owner and the Construction Manager agree upon the adjustments in the GMP or the date of Substantial Completion or date of Final Completion, for a change in the Work directed by an Interim Directed Change, such agreement shall be the subject of an appropriate Change Order.
The Construction Manager shall be obligated to perform changes in the Work that impact the GMP or the estimated Cost of the Work, Construction Manager's Fee, date of Substantial Completion or date of Final Completion once a Change Order has been executed or a written Interim Directed Change has been issued.
As the changed Work is performed, the Constructor shall submit its costs for such Work with its application for payment beginning with the next application for payment within thirty (30) Days of the issuance of the Interim Directed Change.