Examples of Guaranteed Mechanical Completion Date in a sentence
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Parties agree that Contractor’s sole remedy for such delay shall be an adjustment to the Guaranteed Mechanical Completion Date pursuant to a Change Order.
If the milestone required by the Guaranteed Permitting Completion Date or the Guaranteed Mechanical Completion Date is not achieved within thirty (30) days after such date (each, a “Date Certain”), Purchaser may, upon five (5) days’ prior written notice to Seller, elect to terminate this Agreement without liability or further obligation of any kind on the part of Purchaser.
The Guaranteed Mechanical Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Futures trading became standardized in the United States in the mid-1800’s with the establishment of the Chicago Board of Trade (CBoT), which allowed speculators to purchase contracts on agricultural commodities, mainly grains, that were not yet harvested at a set price.