Geotechnical Baseline Report definition

Geotechnical Baseline Report. (GBR) means a single source contract document containing measurable contractual descriptions of the geotechnical conditions to be anticipated or to be assumed to be anticipated during construction;
Geotechnical Baseline Report means the report prepared by [ ], dated [ ], regarding geotechnical conditions at the Project Site.
Geotechnical Baseline Report is described in Section 3.2.1 (Drawings and Reports) of Appendix B-2.

Examples of Geotechnical Baseline Report in a sentence

  • The Bidding Documents contain a Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR).

  • Geotechnical Baseline Report: The Bidding Documents contain a Geotechnical Baseline Report (GBR).

  • Anticipated geotechnical conditions are presented in the Geotechnical Baseline Report (GBR) and Geotechnical Data Reports (GDRs).

  • Under H.R. 4973, FEMA would be required to review the nation’s flood maps, and for the first time, map the nation’s 500-year floodplain.

  • The Contractor shall give written notice to Owner and Engineer of (a) subsurface or latent physical conditions at the Site which differ materially from those indicated in the Geotechnical Baseline Report or other Contract Documents or (b) unknown physical conditions at the Site of an unusual nature that differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the Contract Documents.

  • Except with respect to the Geotechnical Baseline Report and the Geotechnical Data Report, the Department does not warrant the accuracy of any such data, and the Offeror is at sole risk for any conclusions drawn from such data, either expressly or by implication.

  • MDOT is currently in the process of developing a Geotechnical Baseline Report (“GBR”) for the tunnel, which will be provided in the RFP.

  • The Geotechnical Baseline Report has been prepared in accordance with the guidelines and practices described in the Geotechnical Baseline Reports for Construction, Suggested Guidelines, published by ASCE, 2007.

  • A concept that is worthy of consideration is the Geotechnical Baseline Report that aims to establish a contractual understanding of the subsurface site conditions, referred to as a baseline (ASCE 1997).

  • In the event of a potential variation from the baseline parameters presented in the Geotechnical Baseline Report, perform testing as agreed with the Company.


More Definitions of Geotechnical Baseline Report

Geotechnical Baseline Report means the report so designated to be prepared by the Design-Builder pursuant to Stage 1 Preliminary Services set forth in Appendix 2.
Geotechnical Baseline Report means the report dated October 20, 2011 entitled ‘Geotechnical Baseline Report for Bored Tunnels’ located in the Data Room.

Related to Geotechnical Baseline Report

  • Geotechnical engineer means a professional engineer registered with the Association of Professional Engineers, Geologists, and Geophysicists of the Northwest Territories and whose principal field of specialization is the design and construction of earthworks in a permafrost environment;

  • Geotechnical report or "geotechnical analysis" means a scientific study or evaluation conducted by a qualified expert that includes a description of the ground and surface hydrology and geology, the affected land form and its susceptibility to mass wasting, erosion, and other geologic hazards or processes, conclusions and recommendations regarding the effect of the proposed development on geologic conditions, the adequacy of the site to be developed, the impacts of the proposed development, alternative approaches to the proposed development, and measures to mitigate potential site-specific and cumulative geological and hydrological impacts of the proposed development, including the potential adverse impacts to adjacent and down-current properties. Geotechnical reports shall conform to accepted technical standards and must be prepared by qualified professional engineers or geologists who have professional expertise about the regional and local shoreline geology and processes.

  • Independent Engineering Report means a report, in form and substance satisfactory to the Administrative Agent and each of the Lenders, prepared by an Independent Engineer, addressed to the Administrative Agent and the Lenders with respect to the Oil and Gas Properties owned by the Borrower or its Subsidiaries (or to be acquired by the Borrower or any of its Subsidiaries, as applicable) which are or are to be included in the Borrowing Base, which report shall (a) specify the location, quantity, and type of the estimated Proven Reserves attributable to such Oil and Gas Properties, (b) contain a projection of the rate of production of such Oil and Gas Properties, (c) contain an estimate of the net operating revenues to be derived from the production and sale of Hydrocarbons from such Proven Reserves based on product price and cost escalation assumptions specified by the Administrative Agent and the Lenders, and (d) contain such other information as is customarily obtained from and provided in such reports or is otherwise reasonably requested by the Administrative Agent or any Lender.

  • Engineering Report means either an Independent Engineering Report or an Internal Engineering Report.

  • Initial Engineering Report means the engineering report concerning Oil and Gas Properties of Loan Parties dated as of June 30, 2006 prepared by Netherland, Xxxxxx & Associates and XxXxxxxx & XxxXxxxxxxx.

  • Engineering Reports has the meaning assigned such term in Section 2.07(c)(i).

  • Acoustic Assessment Report means the report, prepared in accordance with Publication NPC-233 and Appendix A of the Basic Comprehensive User Guide,by HGC Engineering and dated August 22, 2008 submitted in support of the application, that documents all sources of noise emissions and Noise Control Measures present at the Facility and includes all up-dated Acoustic Assessment Reports as required by the Documentation Requirements conditions of this Certificate to demonstrate continued compliance with the Performance Limits following the implementation of any Modification.

  • conformity assessment body means a body that performs conformity assessment activities including calibration, testing, certification and inspection;

  • Site Assessment means an environmental assessment report for the Mortgaged Property prepared at Borrower’s expense by a qualified environmental consultant engaged by Borrower, or by Lender on behalf of Borrower, and approved by Lender, and in a manner reasonably satisfactory to Lender, based upon an investigation relating to and making appropriate inquiries to evaluate the risks associated with Mold and any existence of Hazardous Materials on or about the Mortgaged Property, and the past or present discharge, disposal, release or escape of any such substances, all consistent with the most current version of the ASTM 1527 standard (or any successor standard published by ASTM) and good customary and commercial practice.

  • Phase I assessment as described in, and meeting the criteria of, (i) Chapter 5 of the FNMA Multifamily Guide or any successor provisions covering the same subject matter in the case of a Specially Serviced Mortgage Loan as to which the related Mortgaged Property is multifamily property or (ii) the American Society for Testing and Materials in the case of Specially Serviced Mortgage Loan as to which the related Mortgaged Property is not multifamily property.

  • Phase I Environmental Report means a report by an Independent Person who regularly conducts environmental site assessments in accordance with then current standards imposed by institutional commercial mortgage lenders and who has a reasonable amount of experience conducting such assessments.

  • Survey Report means a report of the results of a Survey, containing the information set out in clause 12.4 and Schedule 6.

  • Project Management Report means each report prepared in accordance with Section 4.02 of this Agreement;

  • Technical Report means a report prepared and filed in accordance with this Instrument and Form 43-101F1 Technical Report that includes, in summary form, all material scientific and technical information in respect of the subject property as of the effective date of the technical report; and

  • Environmental Impact Assessment means a systematic examination conducted to determine whether or not a programme, activity or project will have any adverse impacts on the environment;

  • Base Case Projections means the initial forecast for the Project prepared as of the Effective Date using the Base Case Financial Model.

  • Environmental impact statement means a detailed written statement as required by section 102(2)(C) of the Act.

  • Feasibility Report means a detailed written report of the results of a comprehensive study on the economic feasibility of placing the Property or a portion thereof into Commercial Production and shall include a reasonable assessment of the mineral ore reserves and their amenability to metallurgical treatment, a description of the work, equipment and supplies required to bring the Property or a portion thereof into Commercial Production and the estimated cost thereof, a description of the mining methods to be employed and a financial appraisal of the proposed operations supported by an explanation of the data used therein;

  • Benchmarking Report means the report produced by the Supplier following the Benchmark Review and as further described in this Framework Schedule 7;

  • Physical Conditions Report means, with respect to the Property, a report prepared by a company satisfactory to Lender regarding the physical condition of the Property, satisfactory in form and substance to Lender in its sole discretion, which report shall, among other things, (a) confirm that the Property and its use complies, in all material respects, with all applicable Legal Requirements (including, without limitation, zoning, subdivision and building laws) and (b) include a copy of a final certificate of occupancy with respect to all Improvements on the Property.

  • Development Report means a written account of Licensee’s progress under the Development Plan having at least the information specified on Appendix B to this Agreement, and shall be sent to the address specified on Appendix B.

  • Baseline area means any intra- state area (and every part thereof) des- ignated as attainment or unclassifiable under section 107(d)(1)(A)(ii) or (iii) of the Act in which the major source or major modification establishing the minor source baseline date would con- struct or would have an air quality im- pact for the pollutant for which the baseline date is established, as follows: equal to or greater than 1 μg/m3 (an- nual average) for SO2, NO2, or PM10; or equal or greater than 0.3 μg/m3 (annual average) for PM2.5.(ii) Area redesignations under section 107(d)(1)(A)(ii) or (iii) of the Act cannot intersect or be smaller than the area of impact of any major stationary source or major modification which:

  • Phase I Report means, with respect to any Facility, a report that (i) conforms to the ASTM Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process, E 1527, (ii) was conducted no more than six months prior to the date such report is required to be delivered hereunder, by one or more environmental consulting firms reasonably satisfactory to Administrative Agent, (iii) includes an assessment of asbestos-containing materials at such Facility, (iv) is accompanied by (a) an estimate of the reasonable worst-case cost of investigating and remediating any Hazardous Materials Activity identified in the Phase I Report as giving rise to an actual or potential material violation of any Environmental Law or as presenting a material risk of giving rise to a material Environmental Claim, and (b) a current compliance audit setting forth an assessment of Holdings’, its Subsidiaries’ and such Facility’s current and past compliance with Environmental Laws and an estimate of the cost of rectifying any non-compliance with current Environmental Laws identified therein and the cost of compliance with reasonably anticipated future Environmental Laws identified therein.