The Foundation Package Submittal is the initial scope of work requiring a building permit to begin construction.
No later than 3 months after the Site Development Package/Schematic Design Submittal, Developer will prepare and deliver to County an electronic Foundation Package Submittal.
Preliminary development of the Site Preparation and Foundation Package inclusive of necessary geotechnical and site utility service termination, rerouting or connection scope of work and coordination of environmental scope of work with the Commissions environmental consultant.
Within ten days after the County approves the Foundation Package Submittal and issues the Foundation Permit, Developer will commence construction of the Project.
No later than 3 months after County’s approval of the Foundation Package, Developer will prepare and deliver to County an electronic Core and Shell Package Submittal.
Final development of the Site Preparation and Foundation Package inclusive of necessary geotechnical and site utility service termination, rerouting or connection scope of work and coordination of environmental scope of work with the Commission’s environmental consultant.
No later than three (3) months after the Site Development Package/Schematic Design Submittal, Developer will prepare and deliver to County an electronic Foundation Package Submittal.
Within ten (10) days after the County approves the Foundation Package Submittal and issues the Foundation Permit, Developer will commence construction of the Sublease Project.