Field Change Request definition

Field Change Request means any request for a minor adjustment or variation in the construction that does not increase or decrease ** Omitted pursuant to a confidential treatment request. The confidential portion has been filed separately with the SEC. the cost of the work by more than Two Thousand Five Hundred Dollars ($2,500.00), and is occasioned by unforeseen on-site conditions and suggested by ** or Com-Site or a subcontractor of either of them, that requires prompt attention to avoid a scheduling delay or because of impending unavailability of a particular trade, or for which it is not customary to submit a formal change order or revision of drawings. Landlord shall require ** and Tenant shall require Com-Sits and the Consulting Architect to meet with representatives of Landlord and Tenant as necessary, but no less often than once every month, to review all disputed change orders that have been made in accordance with this Section. The parties shall negotiate in good faith to reach a mutually acceptable determination of the relative rights and liabilities of each of the parties in connection with the disputed change orders. If such agreement is not reached the matter shall be resolved as provided in Section 37 of this Lease.

Examples of Field Change Request in a sentence

  • If either party shall fail to disapprove a Field Change Request within the time limits set forth in the preceding sentence, such request shall be deemed to have been approved.

Related to Field Change Request

  • Change Request means a change request made in accordance with Section 4 below and in the form made available by SAP from time to time or included in the Order Form.

  • Exchange Request shall have the meaning specified in Section 7(b) hereof.

  • Change Order Request means a written request or proposal for a Change Order submitted by either Company or Contractor and including:

  • New Service Request means an Interconnection Request, a Completed Application, or an Upgrade Request.

  • Change of Scope Request shall have the meaning set forth in Clause 13.2 (ii); “Change of Scope Order” shall have the meaning set forth in Clause 13.2 (iv); “Completion Certificate” shall have the meaning set forth in Clause 12.2; “Construction” shall have the meaning set forth in Clause 1.2 (f);