FGD System definition
Examples of FGD System in a sentence
NPDES Permit Modification Permit modification will incorporate additional waste streams generated by operation of the Unit 5 FGD System.
Included with the FGD System are the raw limestone facilities required for receiving, unloading, grinding, preparation and transfer of limestone to the FGD System proper.
In the event that Provisional Acceptance of an FGD System is not achieved by a Guaranteed Provisional Acceptance Date that is after December 31, 2009 then, unless reduced pursuant to Section 8.2.3.4, the stated Late Provisional Acceptance Payment shall apply for each day beginning with the Guaranteed Provisional Acceptance Date and ending with the day before Provisional Acceptance is achieved.
In the event that the actual Mercury Removal is less than the guaranteed Mercury Removal, Owner shall asses Contractor $1,000,000 per each FGD System where the performance guarantee was not achieved, and the Mercury Removal criteria for successful completion shall be deemed to have occurred as of the date of the Performance Test PA.
With respect to each FGD System, Owner shall obtain all permits as required for construction for which it is responsible on or before September 1, 2007.
For each of the Output Guarantees for a FGD System, System output shall satisfy the guaranteed value as a minimum.
The Guaranteed Substantial Completion Date for each FGD System at each Facility shall be the date that is ninety (90) days after date on which such System achieves Provisional Acceptance.
If the performance guarantee is met after re-testing by Contractor, within the ninety (90) day cure period, Owner shall return to Contractor the above-referenced payments if such amounts were paid to Owner pursuant to Article 7.2.2 for each FGD System where the performance guarantee was achieved.
The Work necessary for and included in the milestone identified in Exhibit 15 as “Ready for Flue Gas to Scrubber” for each FGD System at each Facility shall be completed before 23:59 December 31, 2009, and the Guaranteed Provisional Acceptance Date for each FGD System shall be a date not later than one hundred five (105) days after the first day of the Scheduled Outage Period set forth in the Approved Project Schedule for the final tie-in outage for that System.
Pressure drop through FGD System as provided in Section 1.1.3 of Exhibit 6.