In the event that the SPD fails to endorse the certificate within [7 (seven) days] of its issuance, then the certificate will be deemed to have been issued and endorsed, and the grant of access rights of the Internal Power Evacuation Infrastructure from the SPPD to SPD shall be deemed to have been completed.
Upon the expiry of 15 (fifteen) Days from such assessment the SPPD shall issue a certificate to the SPD as per the format prescribed under Annexure B certifying the completion, and grant of all necessary access rights to the SPD, of the Internal Power Evacuation Infrastructure (Completion Notice), which shall be endorsed by the SPD within 7 (seven) Days of its issue.
The grant of access rights of the Internal Power Evacuation Infrastructure to the SPD shall be deemed to be complete on the date of endorsement of this certificate by the SPD.
Pursuant to Article 3.2(b) of the Implementation Support Agreement, the Internal Power Evacuation Infrastructure has been completed in accordance with the terms of the Implementation Support Agreement and all necessary access rights to the Internal Power Evacuation Infrastructure have been granted to the SPD.
TUSCO LTD, after considering the expenditure for development of Infrastructure, will collect one-time Solar Power Park development expenses towards capital cost for Infrastructure such as Internal Power Evacuation Infrastructure (33/220 kV Pooling substation & Transmission Lines), Roads, Admin Building, Water Supply, Drainage System, Boundary fence, Security, preliminary Land development etc.
Provided that, the SPPD shall, at least 15 (fifteen) Days prior to the proposed completion of the Internal Power Evacuation Infrastructure, invite the SPD to undertake an assessment of the Internal Power Evacuation Infrastructure.
In the event the LC is not replenished within 7 (seven) days, TUSCO shall have right to regulate the SPD's access to the Internal Evacuation Infrastructure by issuing a one-month advance notice to the SPD in writing.
The operation and maintenance of the Internal Power Evacuation Infrastructure, from its completion as per Article 3.2(b) and for the Term of this Agreement, shall be carried out by the SPPD, or its authorized representative, at its own cost and risk.
If the SPD fails to achieve the COD of the Project (as per the terms of the PPA) within [6 (six) Months] after the expiry of the original SCSD of the Project due to the SPPD's failure, to construct and commission the Internal Power Evacuation Infrastructure or to ensure connectivity to the UPPTCL Substation, where such failure has not occurred as a consequence of a Force Majeure Event or for reasons attributable to the SPD, then the SPD shall be entitled to terminate this Agreement.