Electrical Works Completion definition

Electrical Works Completion has the meaning set forth in Section 7.3.
Electrical Works Completion with respect to an individual circuit of Electrical Works and equipment associated therewith means the achievement of the following milestones:
Electrical Works Completion with respect to an individual circuit of Electrical Works and equipment associated therewith means the achievement of the following milestones: The padmount foundations have been completed; all of the Electrical Works including the installation of all grounding, necessary to energize the WTGs, are completed in accordance with the requirements of this Agreement; subject to Punch List Items, all materials and equipment associated with such Electrical Works have been installed in accordance with the Technical Specifications, the Commissioning checklist set forth in Exhibit 1 and Exhibit 3B, and the other requirements of this Agreement and checked for adjustment; such Electrical Works and all other Infrastructure Facilities necessary to achieve connection of such WTGs to the electricity transmission system interconnected at the Project Substation, are energized; all of the Electrical Works necessary to achieve connection of such padmount transformers to the Project Substation in accordance with this Agreement have been installed, insulated, protected and tested, including synchronization with such system; subject to Punch List Items, all of such Electrical Works have been properly constructed, installed, insulated and protected where required for such operation, correctly adjusted, tested and commissioned, are mechanically, electrically and structurally sound as set forth in the Technical Specifications, and can be used safely in accordance with the Contract Documents, Applicable Laws and Applicable Standards; Contractor has prepared and submitted a list of Punch List Items with respect to such circuit of Electrical Works; and Owner has accepted or is deemed to have accepted an Electrical Works Completion Certificate with respect to such Electrical Works pursuant to Section 7.8.

Examples of Electrical Works Completion in a sentence

  • In connection with and as a condition to the achievement of Electrical Works Completion for a particular circuit and the achievement of WTG Mechanical Completion as to each WTG, Contractor shall develop a list (each, an “Interim Punch List”) setting forth parts of the Work which remain to be performed in order to confirm that the Work fully complies with the terms of this Agreement.

  • HUD will use its reasonable endeavours to advise the Provider of any such request received by it that relates to Confidential Information of the Provider and to the extent reasonably practicable, will allow the Provider a reasonable opportunity to comment on any Confidential Information HUD proposes to, or is required to, disclose under those Acts.

  • Such certificate shall include the results of all testing relevant to achievement of such milestone and otherwise contain sufficient detail to enable Owner to determine that Contractor has achieved Access Road Completion, Foundation Completion, Electrical Works Completion, WTG Mechanical Completion, Availability Completion, Project Mechanical Completion or Final Completion, as the case may be.

  • Electrical Works Completion, WTG Mechanical Completion, Project Mechanical Completion, and Final Completion.

  • Such certificate shall include the results of all testing relevant to achievement of such milestone and otherwise contain sufficient detail to enable Owner to determine that Contractor has achieved Access Road Completion, Foundation Completion, Electrical Works Completion, WTG Mechanical Completion, Project Mechanical Completion or Final Completion, as the case may be.

  • When Contractor believes that it has achieved any of Access Road Completion, Foundation Completion, Electrical Works Completion, WTG Mechanical Completion, Project Mechanical Completion or Final Completion, it shall deliver to Owner a completed Access Road Completion Certificate, Foundation Completion Certificate, Electrical Works Completion Certificate, WTG Mechanical Completion Certificate, Project Mechanical Completion Certificate or Final Completion Certificate, as the case may be.