Document G704 definition

Document G704 means Document G704-2017, entitled Certificate of Substantial Completion, as may be amended, a trademarked form created by the American Institute of Architects and used by the GLO to substantiate draw requests and Project completion.

Examples of Document G704 in a sentence

  • The performance measure documenting satisfactory completion of Deliverables will be a completed Application and Certificate for Payment (AIA Document G702), Schedule of Contract Values (AIA Document G703), and a Certificate of Substantial Completion (AIA Document G704), or its equivalent (see Appendix 1), showing 100% of the project completed, including all retainage amounts paid.

  • The performance measure documenting satisfactory completion of Deliverables will be a completed Application and Certificate for Payment (AIA Document G702), Schedule of Contract Values (AIA Document G703), and a Certificate of Substantial Completion (AIA Document G704), or its equivalent (see Appendix 1), showing 100 percent (100%) of the project completed, including all retainage amounts paid.

  • Tenant shall submit to Landlord on or before the Lease Commencement Date (as defined in the Lease) a Certificate of Substantial Completion, AIA Document G704, by its Tenant Improvement Architect for the Final Tenant Improvement Plans, a copy of all final inspection cards for the Tenant Improvements signed by the appropriate City of Santa ▇▇▇▇▇ inspector and the Temporary Certificate of Occupancy from the City of Santa ▇▇▇▇▇.

  • Tenant shall submit to Landlord on or before the Lease Commencement Date (as defined in the Lease) a Certificate of Substantial Completion, AIA Document G704, by its Tenant Improvement Architect for the Final Tenant Improvement Plans, a copy of all final inspection cards for the Tenant Improvements signed by the appropriate City of Palo Alto inspector and the Temporary Certificate of Occupancy from the City of Palo Alto.

  • AIA Document G704, Certificate of Substantial Completion, or other substitute form supplied and required by the County shall be used.

  • The performance measure documenting satisfactory completion of Deliverables will be a completed Application and Certificate for Payment (AIA Document G702), Schedule of Contract Values (AIA Document G703), and a Certificate of Substantial Completion (AIA Document G704), or its equivalent (See Appendix 1), showing 100 percent of the project completed, including all retainage amounts paid.

  • AIA Document G704 is a copyrighted work and may not be reproduced or excerpted from in substantial part without the express written permission of the AIA.

  • The Construction Manager shall provide any information necessary for the Architect to issue and signs a Certificate of Substantial Completion, AIA Document G704 (or similar document) if required by Owner.

  • The Project architect shall have issued its “Certificate of Substantial Completion” (AIA Document G704 or its substantial equivalent) stating that the Plaza is substantially complete in substantial accordance with the Project Permits.

  • A written certification from the Inspector in the form of AIA Document G704, executed by the Borrower’s general contractor and the Borrower, certifying (i) that completion has occurred; (ii) the date of completion; (iii) that direct connection has been made to all appropriate utility facilities; and (iv) that the Improvements are ready for occupancy.