DBOM definition
Examples of DBOM in a sentence
The McKinstry family of companies provides full design, build, operate, and maintain (DBOM) services as well as ESCO services.
The ▇▇▇▇▇▇▇▇▇ family of companies provides full design, build, operate, and maintain (DBOM) services as well as ESCO services.
In no event shall the rejection or modification of any such Capital Modification by the BWS relieve the DBOM Contractor of its obligations under this Service Agreement.
The DBOM Contractor shall be responsible for any schedule and cost consequences which may result from the submission of materially incorrect or incomplete information.
If any component index is no longer published at the time that adjustment is to be calculated, or if the base or method of calculation used for the component index is altered, the calculation shall be made using a comparable similar index or method mutually agreed upon by the DBOM Contractor and the BWS.
In the event that the DBOM Contractor or any Subcontractor fails at any time to comply with Applicable Law (including any Governmental Approval) it shall take all actions required by subsection 4.4(E) (Fines, Penalties and Remediation), including immediately correcting such failure and resuming compliance with Applicable Law.
In addition, the DBOM Contractor shall be entitled to an adjustment of the Fixed Design-Build Price determined pursuant to Section 19.4 (Schedule Relief and Related Price Relief) for the number of days of delay caused by the applicable Governmental Body, as calculated in accordance with this subsection.
Upon any such termination, the BWS shall have all of the rights provided in Article 17 (Breach, Default, Remedies and Termination) upon a termination of the DBOM Contractor for cause.
The DBOM Contractor’s initial notice shall be issued by telephone or in person to the Officer-in-Charge and shall be followed thereafter by written notice provided in accordance with Section 19.2 (Uncontrollable Circumstance Claim Procedures).
Any adjustment under this subsection shall be limited to the number of days any such Governmental Body delay actually causes delay in the DBOM Contractor’s critical path completion schedule after the exercise of all commercially reasonable mitigation efforts by the DBOM Contractor.