Date of Availability definition

Date of Availability meansNotice to Proceed Date
Date of Availability means the day on which, or as of which, depending on
Date of Availability means the date 20 days after shipment (for the countries: Armenia, Belarus, Georgia, Kazakhstan, Kirghizia, Moldova, Russia and Ukraine 30 days), or, for Additional Licenses the date the Customer has copied the Program.

Examples of Date of Availability in a sentence

The schedule shall begin with the Date of Availability and end with the Actual Completion Date proposed by the Design-Build Team.

The schedule shall begin with the Date of Availability and end with the actual Completion Date proposed by the Design-Build Team.

It is the intent of these specifications that the Contractor shall commence work on the Date of Availability specified in the Project Special Provisions and/or Proposal or as soon thereafter as practicable.

If such approval is given and the Contractor does begin work prior to Date of Availability, the Owner will assume no responsibility for any delays caused prior to Date of Availability by any reason whatsoever, and such delays, if any, will not constitute a valid reason for extending the completion date.

The Contractor shall not begin work prior to the Date of Availability without written approval of the Engineer.


More Definitions of Date of Availability

Date of Availability means the date on which USA accepts the project as substantially complete.
Date of Availability meansNotice to Proceed Date”.