Contract Float definition

Contract Float means the number of days that an activity or a sequence of activities does not necessarily have to start or end on the scheduled dates to maintain the schedule, or as a minimum, the number of days that an activity may be delayed from its early start date without delaying completion of the Work beyond the Contract Time for Substantial Completion or Final Acceptance.

Examples of Contract Float in a sentence

  • Total and Contract Float shall be available to JEA, consultants, or the Contractor to accommodate changes in the Work or to mitigate the effect of events which may delay performance or completion.

  • Total and Contract Float are an expiring resource available to all parties, acting in good faith, as needed to meet the contract milestones.

  • Use of FloatTotal Float and Contract Float are not for the exclusive use or benefit of either JEA or the Contractor, but must be used in the best interest of completing the project within the Contract Time relative to the contract milestones.

  • Since Contract Float belongs to the project, the contractor shall not be entitled to any extension in contract time or recovery for any delay incurred because of extensions of an early completion date until all Contract Float is used or consumed and performance or completion of the work extends beyond the contract time.

  • Total Float and Contract Float belong to the Project and are not for the exclusive benefit of any party.

  • Contract Float and Total Float shall be available to the DISTRICT, consultants, or the CONTRACTOR to accommodate changes in the WORK or to mitigate the effect of events which may delay performance or completion.

  • Adjustment of the Contract Times will be granted only when the Contract Float has been fully utilized and only when the revised date of completion of the Work has been pushed beyond the Contract completion date.

  • Neither the Contract Time nor Contract Amount shall be changed due to a delay in Contractor’s early completion date until all the corresponding Contract Float available in the Record Schedule at the start of the delay is used and performance of the specified Work extends necessarily beyond that Contract Time.

  • Since Contract and Total Floats belong to the Project, the CONTRACTOR shall not be entitled to any extension in Contract Time or recovery for any delay incurred because of extensions in an early completion date until all Contract Float is used or consumed and performance or completion of the WORK extends beyond the Contract Time.

  • Contract Float is the number of daysbetween the CONTRACTOR’s anticipated date for early completion of the WORK, or specified part, and the corresponding Contract Time.

Related to Contract Float

  • Test Facility means any WRAS suitably accredited test laboratory;

  • Contract Fee means the lump sum rates as outlined in Schedule ‘B’ – Quote Form.

  • Commissioning test means tests applied to the Generating Facility, after completion of the construction of the Generating Facility, in order to verify that the Generating Facility may be released for Operation.

  • Fixed wing turbine powered aircraft means an aircraft that:

  • Dry cleaning facility means an establishment with one or more dry cleaning systems.

  • CONTRACT END DATE Contract performance shall terminate as of December 31, 2027, with no new obligations being incurred after this date unless the Contract is properly amended, provided that the terms of this Contract and performance expectations and obligations shall survive its termination for the purpose of resolving any claim or dispute, for completing any negotiated terms and warranties, to allow any close out or transition performance, reporting, invoicing or final payments, or during any lapse between amendments. CERTIFICATIONS: Notwithstanding verbal or other representations by the parties, the “Effective Date” of this Contract or Amendment shall be the latest date that this Contract or Amendment has been executed by an authorized signatory of the Contractor, the Department, or a later Contract or Amendment Start Date specified above, subject to any required approvals. The Contractor certifies that they have accessed and reviewed all documents incorporated by reference as electronically published and the Contractor makes all certifications required under the Standard Contract Form Instructions and Contractor Certifications under the pains and penalties of perjury, and further agrees to provide any required documentation upon request to support compliance, and agrees that all terms governing performance of this Contract and doing business in Massachusetts are attached or incorporated by reference herein according to the following hierarchy of document precedence, the applicable Commonwealth Terms and Conditions, this Standard Contract Form, the Standard Contract Form Instructions and Contractor Certifications, the Request for Response (RFR) or other solicitation, the Contractor’s Response (excluding any language stricken by a Department as unacceptable, and additional negotiated terms, provided that additional negotiated terms will take precedence over the relevant terms in the RFR and the Contractor’s Response only if made using the process outlined in 801 CMR 21.07, incorporated herein, provided that any amended RFR or Response terms result in best value, lower costs, or a more cost effective Contract.

  • Total Contract Price/Project Cost/TCO means the price payable to Service Provider over the entire period of Contract for the full and proper performance of its contractual obligations.

  • Contract Item or “Contract Items” means the list of items identified in Section

  • Triage facility means a short-term facility or a portion

  • principal contractor means an employer appointed by the client to perform construction work;

  • Contract base bid means the total dollar amount a contractor bids on a contract without factoring any bid incentive or percentage reductions to the bid amount.

  • Wind Turbine means a mechanical/electrical system that converts the kinetic energy of blowing wind into mechanical or electric power.

  • Commissioning Tests means all of the procedures and tests which, in accordance with the Reasonable and Prudent Standard, and in compliance with industry guidelines, practices and standards, are:

  • The Contract Price/Project Cost means the price payable to the Vendor under the Contract for the full and proper performance of its contractual obligations.

  • Transit-oriented facility means a facility that houses a transit station in a manner that promotes transit ridership or passenger rail use.

  • Facility Site shall have the meaning set forth in the recitals to the Facility Site Lease.

  • Contract Work means everything required to be furnished and done by the Contractor by any one or more of the parts of the Contract referred to in Article 1, except Extra Work as hereinafter defined.

  • Construction Phase means that Phase of the Project which shall commence after the Authority provides the Trade Contractor with written Notice to Proceed with the Construction Phase.

  • Project Facility means facility being one or more of the following facilities as specified in the Special Conditions of Contract, being developed in accordance with the Project and the Detailed Project Implementation Report and includes all its buildings, equipment, facilities, software and systems and includes without limitation, where the circumstances so require, any expansion thereof from time to time and may include any new location to be separately mentioned in the Special Conditions of Contract.

  • Construction Completion Date means the date by which the overall development of the Project is completed in accordance with the provisions of this Agreement and when the Construction Completion Certificate is issued by the Independent Engineer as per Article 14.1.

  • Overhaul means the restoration of an aircraft or aircraft component using methods, techniques, and practices acceptable to the Authority, including disassembly, cleaning, and inspection as permitted, repair as necessary, and reassembly; and testing in accordance with approved standards and technical data, or in accordance with current standards and technical data acceptable to the Authority, which have been developed and documented by the State of Design, holder of the type certificate, supplemental type certificate, or a material, part, process, or appliance approval under Parts Manufacturing Authorisation (PMA) or Technical Standard Order (TSO);

  • Lower tier subcontractor means any party entering into an agreement with the SUBCONTRACTOR or any Lower Tier SUBCONTRACTOR for the furnishing of supplies or services required for performance of this Subcontract.

  • Staging pile means an accumulation of solid, non- flowing remediation waste (as defined in this section) that is not a containment building and that is used only during remedial operations for temporary storage at a facility. Staging piles must be designated by the Director according to the requirements of § 264.554 of this regulation.

  • Original contractor means a person, including an owner-builder, that contracts with an owner to provide preconstruction service or construction work.

  • Auction Final Price means the relevant auction final price that may be published by ISDA or any administrator of any auction coordinated by ISDA from time to time and that would be applicable to the senior, unsecured debt obligations issued or guaranteed by the relevant

  • Project Completion Date means the date on which the Completion Certificate is issued;