ComEd Zone definition
Examples of ComEd Zone in a sentence
Notwithstanding the above provisions of this Article 8, the obligations of Parties serving load in the ComEd Zone during the Interim Period, as those terms are defined in Schedule 17, shall be determined as set forth in Schedule 17.
Notwithstanding the above provisions of this Article 9, any charges related to the obligations of Parties serving load in the ComEd Zone during the Interim Period, as those terms are defined in Schedule 17, shall be determined as set forth in Schedule 17.
Notwithstanding anything to the contrary herein, the total dollar amount apportioned to the ComEd Zone for the Baseline Upgrades shall not exceed $75,000.
PJM shall make a true-up adjustment to the ComEd Zone and BGE Zone no later than the May/June 2018 billing cycle to reconcile any difference, plus or minus, between the amount not to exceed $75,000 in the Settlement Agreement and the amounts actually paid on behalf of the ComEd Zone for the Baseline Upgrades.
Calculate the difference between the Revised ComEd Zone Allocated Cost of 6.13% and the ComEd Zone’s new annual load ratio share update percentage, as determined by Schedule 12 of the PJM Tariff.
Consistent with the annual update procedures set forth in the Tariff, Schedule 12, PJM, on the Implementation Date as defined in Section 1.4 below, shall file, consistent with Section 4.1 infra, revised tariff sheets to implement the revised cost allocations for the Baseline Upgrades for the period May 1, 2017 through December 31, 2017 for the Baseline Upgrades to reflect the Revised ComEd Zone Allocated Cost and the Revised BGE Zone Allocated Cost, attached hereto as Exhibit A (“Revised Tariff”).
Notwithstanding the agreed-upon amendments to the Original Cost Allocations, Exelon agrees that the ComEd Zone and BGE Zone shall continue to pay the Original Cost Allocations until the Implementation Date as defined below in Section 1.4.
On or before January 1, 2018, PJM shall file revised tariff sheets to implement the revised cost allocations for the Baseline Upgrades for the period January 1, 2018 through May 31, 2018, to reflect the Revised ComEd Zone Allocated Cost and the Revised BGE Zone Allocated Cost, as set forth in this Settlement Agreement.
The bottom line is that the Settlement Agreement reduces the allocation of costs to the ComEd Zone not to exceed a total of $75,000 and increases the allocation of costs to the BGE Zone by the amount corresponding to the adjustments agreed upon in the Settlement Agreement.