Voltage Regulators. Whenever the Generating Facility is operated in parallel with the Transmission or Distribution System as applicable and voltage regulators are capable of operation, Interconnection Customer shall operate the Generating Facility with its speed governors and voltage regulators in automatic operation. If the Generating Facility’s voltage regulators are not capable of such automatic operation, Interconnection Customer shall immediately notify Transmission Provider’s system operator, or its designated representative, and ensure that such Generating Facility’s reactive power production or absorption (measured in MVARs) are within the design capability of the Generating Facility’s generating unit(s) and steady state stability limits. Interconnection Customer shall not cause its Generating Facility to disconnect automatically or instantaneously from the Transmission or Distribution System, as applicable, or trip any generating unit comprising the Generating Facility for an under or over frequency condition unless the abnormal frequency condition persists for a time period beyond the limits set forth in ANSI/IEEE Standard C37.106, or such other standard as applied to other generators in the Local Balancing Authority on a comparable basis.

Appears in 20 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Voltage Regulators. Whenever the Large Generating Facility is operated in parallel with the Transmission or Distribution System as applicable and voltage regulators are capable of operation, Interconnection Customer shall operate the Large Generating Facility with its speed governors and voltage regulators in automatic operation. If the Large Generating Facility’s 's voltage regulators are not capable of such automatic operation, Interconnection Customer shall immediately notify Transmission Provider’s 's system operator, or its designated representative, and ensure that such Large Generating Facility’s 's reactive power production or absorption (measured in MVARs) are within the design capability of the Large Generating Facility’s 's generating unit(s) and steady state stability limits. Interconnection Customer shall not cause its Large Generating Facility to disconnect automatically or instantaneously from the Transmission or Distribution System, as applicable, System or trip any generating unit comprising the Large Generating Facility for an under or over frequency condition unless the abnormal frequency condition persists for a time period beyond the limits set forth in ANSI/IEEE Standard C37.106, or such other standard as applied to other generators in the Local Balancing Authority Control Area on a comparable basis.

Appears in 11 contracts

Samples: Surplus Large Generator Interconnection Agreement, Agreement, Agreement

Voltage Regulators. Whenever the Generating Facility is operated in parallel with the Transmission or Distribution System as applicable and voltage regulators are capable of operation, Interconnection Customer shall operate the Generating Facility with its speed governors and voltage regulators in automatic operation. If the Generating Facility’s 's voltage regulators are not capable of such automatic operation, Interconnection Customer shall immediately notify Transmission Provider’s system operator, or its designated representativeDistribution Provider and the ISO, and ensure that the Electric Generating Unit operates as specified in Article 9.6.2 through manual operation and that such Generating Facility’s reactive power production or absorption (measured in MVARs) are within the design capability of the Generating Facility’s 's generating unit(s) and steady state stability limits. Interconnection Customer shall not cause its Generating Facility to disconnect automatically or instantaneously from the Transmission or Distribution System, as applicable, System or trip any generating unit comprising the Generating Facility for an under or over frequency condition unless the abnormal frequency condition persists for a time period beyond the limits set forth in ANSI/IEEE Standard C37.106, or such other standard as applied to other generators in the Local Balancing Authority Control Area on a comparable basis.

Appears in 6 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Voltage Regulators. Whenever the Generating Facility is operated in parallel with the Transmission or Distribution System as applicable and voltage regulators are capable of operation, Interconnection Customer shall operate the Generating Facility with its speed governors and voltage regulators in automatic operation. If the Generating Facility’s voltage regulators are not capable of such automatic operation, Interconnection Customer shall immediately notify Transmission Provider’s system operator, or its designated representative, and ensure that such Generating Facility’s reactive power production or absorption (measured in MVARs) are within the design capability of the Generating Facility’s generating unit(s) and steady state stability limits. Interconnection Customer shall not cause its Generating Facility to disconnect automatically or instantaneously from the Transmission or Distribution System, as applicable, System or trip any generating unit comprising the Generating Facility for an under or over frequency condition unless the abnormal frequency condition persists for a time period beyond the limits set forth in ANSI/IEEE Standard C37.106, or such other standard as applied to other generators in the Local Balancing Authority Control Area on a comparable basis.

Appears in 1 contract

Samples: Generator Interconnection Agreement