Utility Switching Costs Clause Samples
Utility Switching Costs. Utilities Kingston may be requested by the Customer to perform switching on their apparatus to accommodate required maintenance or emergency repairs. In these situations Utilities Kingston will be compensated for associated costs. Such charges are subject to change and will be based on the latest revision of the Utilities Kingston Master Fee Schedule. Utilities Kingston will advise the Customer of charges prior to commencing work except in the case of emergencies or exceptional circumstances.
5.1 Timely exchange of information on upcoming work is essential for proper co-ordination with other work programs. The Utilities Kingston, the System Operator, will co-ordinate requests into their planned work programs.
5.2 From time to time Utilities Kingston schedules power outages for maintenance and upgrades to KINGSTON HYDRO’s sub-transmission and distribution systems. If the customer requests this work be done at times other than those planned by Utilities Kingston, the customer will be responsible for all extra costs, including overtime, to complete the work.
5.3 Utilities Kingston and the Customer will inform each other at least two (2) working days in advance of any planned work which could have an effect on the other's operation. Discussion in detail should be carried out at this advance date. 'On-site' discussions will be held as required.