Utility Relocations. Except as otherwise noted, the DB Contractor shall be responsible for all costs (both direct and indirect) associated with the performance/coordination of all Utility adjustment work within the ROW that remains in conflict following NTP and the performance/coordination of any Utility adjustment work beyond the ROW caused by DB Contractor’s final design. All costs associated with the design and construction of a complete storm sewer system are to be included in the DB Contractor’s Contract Price. The DB Contractor is not entitled to any time extensions caused by delays attributable to Utilities, except for delays due to the discovery of unknown Utilities requiring adjustment or uncooperative Utility Companies as described in Section 8.2.1. Any change in the scope of the Work pursuant to this Section 8.2 shall not be considered a District-Directed Change.