Common use of Utility Delays Clause in Contracts

Utility Delays. Design-Builder shall not be entitled to claim relief for a Utility Delay unless all of the following conditions are satisfied: (a) Design-Builder has provided evidence reasonably satisfactory to VPRA that (i) Design- Builder has fulfilled its obligation under the applicable Utility Agreement(s) to coordinate with the Utility Owner to prevent or reduce the delays, and (ii) Design-Builder has otherwise made diligent efforts to obtain the timely cooperation of the Utility Owner but has been unable to obtain this timely cooperation; and (b) if Design-Builder is responsible for the Relocation, Design-Builder has provided a reasonable Relocation Plan to the Utility Owner and Design-Builder has obtained, or is in a position to timely obtain, all applicable approvals, authorizations, certifications, consents, exemptions, filings, leases, licenses, permits, registrations, options, and/or rulings required by any Governmental Approval or Law to design and construct the Relocation. Design-Builder shall provide an explanation and details demonstrating compliance with the above-stated conditions in the Request for Change Order submitted as provided in Section 12.4.

Appears in 2 contracts

Sources: Design Build Agreement, Design Build Agreement