Common use of Underground Utility Facilities Clause in Contracts

Underground Utility Facilities. To the extent required by Section 4215 of the Government Code, City shall compensate Contractor for the costs of: (1) locating and repairing damage to underground utility facilities not caused by the failure of Contractor to exercise reasonable care; (2) removing or relocating underground utility facilities not indicated in the construction drawings; and (3) equipment necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay caused by failure of City to provide for removal or relocation of such utility facilities.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract