Common use of TIME SCHEDULE FOR COMPLETION Clause in Contracts

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31, 2019. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 2 contracts

Sources: Professional Services Agreement, Professional Services

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31, 2019in the timelines determined by Washoe County Emergency Management. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s 's failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope Statement of Work on the Project shall be diligently performed and be completed no later than December 31, 20192023. Consultant Contractor shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond ConsultantContractor's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove ConsultantContractor's work promptly. Consultant Contractor will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. ConsultantContractor’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Agreement for Services

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31June 30, 20192022. Consultant Contractor shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond ConsultantContractor's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove ConsultantContractor's work promptly. Consultant Contractor will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. ConsultantContractor’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Services Agreements

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31November 15th, 20192018. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, the Scope of Work on the Project shall be diligently performed and be completed no later than December 31March 10, 20192023. Consultant shall be granted time extensions for items within the phases of the Project in writing by County The District if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, CountyThe District's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County The District a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the CountyDistrict.

Appears in 1 contract

Sources: Professional Services

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31August 29th, 20192025. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Agreement for Services

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31February 15, 20192021. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31June 30, 20192025. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly quarterly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on 45 days following the first day end of each month quarter and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly quarterly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31June 30, 20192021. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31September 30, 20192018. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement

TIME SCHEDULE FOR COMPLETION. The Services identified in Exhibit A, Scope of Work on the Project shall be diligently performed and be completed no later than December 31June 30, 20192020. Consultant shall be granted time extensions for items within the phases of the Project in writing by County if the time schedules cannot be met because of delays beyond Consultant's reasonable control, including, but not limited to, County's failure to furnish information, or to approve or disapprove Consultant's work promptly. Consultant will provide to County a monthly report including a schedule identifying progress or work completed, problems or difficulties being encountered, work to be initiated during the following month and other useful information. This report will be submitted on the first day of each month and will be in a format suitable for submittal to other interested agencies. Consultant’s failure to submit promptly the monthly progress report may cause delay in payment from the County.

Appears in 1 contract

Sources: Professional Services Agreement